Wind power plant, California

85 A wind power plant, California

85 A is a 21.3 MW wind power plant in Kern County, California, operated by Wind Wall 1 LLC, and it generated 70,553 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 66th percentile of U.S. wind plants. By 2025 generation it ranks 3,752nd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

21.3 MWNameplate capacity
38%Capacity factor, 2025, 66th percentile, on 21.3 MW net summer
3,752ndU.S. rank by generation, 2025
4 yearsAverage generator age, by MW

How hard does the 85 A plant run compared with other wind plants?

The 85 A plant had a capacity factor of 38% in 2025 on 21.3 MW of net summer capacity, the 66th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 138 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
85 A38%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the 85 A plant generating more or less than last year?

Generation at 85 A fell 0.8% from 2024 to 2025, from 71,157 MWh to 70,553 MWh.

Net generation by period
PeriodMWh
202471,157
202570,553
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20253,524
November 20253,024
October 20254,510
September 20254,255
August 20256,711
July 20257,744
June 20257,705
May 20258,035
April 20257,716
March 20257,989
February 20255,268
January 20254,072
December 20243,206
November 20244,486
October 20244,652
September 20244,457
August 20246,500
July 20245,521
June 20249,058
May 20249,644
April 20247,532
March 20246,117
February 20244,195
January 20245,789

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the 85 A plant?

85 A made 0.0% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. Its share of output is 1.7 times its share of capacity. By capacity it is the 610th largest of 1,877 plants in California, the 4,727th largest of 14,327 in the U.S. and the 1,008th largest of 1,358 wind plants. By 2025 generation it is the 392nd largest of 1,608 generating plants in the state.

85 A within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)21107,4330.0%
Generation (MWh)70,553204,542,8980.0%
Wind capacity (MW)216,4790.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the 85 A plant, and when do they retire?

1 operable generator totals 21.3 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 1 has already retired, totalling 14.1 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s121100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
MON1OperatingOnshore Wind Turbine212021n/a
WGNSRetiredOnshore Wind Turbine1419852019

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the 85 A plant?

EIA lists no joint owners for 85 A. Wind Wall 1 LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the 85 A plant?

85 A is in Tehachapi, Kern County, California, at 35.0958° N, 118.3248° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in California are similar in size?

California has 111 operable wind plants with 6,479 MW of capacity, and 85 A's 21.3 MW is 0% of that.

Wind plants in California around this size
PlantCountyMW2025 MWh
CalPortland Company Mojave WindKern2424,360
Mountain View IIIRiverside2280,725
Voyager Wind IVKern2278,747
85 AKern2170,553
Tehachapi Wind Resource IIKern2047,564
Edom Hills Project 1 LLCRiverside201,557
Rising Tree Wind Farm IIKern2053,735

Source: EIA Forms EIA-860 and EIA-923, 2025.