Skip to main content
RateWatt

Hydro power plant, Maine

Anson Abenaki Hydros hydroelectric power plant, Maine

Anson Abenaki Hydros is a 29 MW hydro power plant in Somerset County, Maine, operated by Eagle Creek Renewable Energy, LLC, and it generated 100,587 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.7% of the generation reported in Maine, and its capacity factor sits at the 80th percentile of U.S. hydro plants. By 2025 generation it ranks 3,383rd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

29 MWNameplate capacity
46%Capacity factor, 2025, 80th percentile, on 25.1 MW net summer
0.7%Of ME generation, 2025
44 yearsAverage generator age, by MW

How hard does the Anson Abenaki Hydros plant run compared with other hydro plants?

The Anson Abenaki Hydros plant had a capacity factor of 46% in 2025 on 25.1 MW of net summer capacity, the 80th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 167 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Anson Abenaki Hydros46%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Anson Abenaki Hydros plant generating more or less than last year?

Generation at Anson Abenaki Hydros fell 13.5% from 2024 to 2025, from 116,313 MWh to 100,587 MWh.

Net generation by period
PeriodMWh
2024116,313
2025100,587
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20257,990
November 20256,250
October 20252,832
September 20253,757
August 20254,263
July 20259,564
June 20258,893
May 202514,143
April 202513,293
March 202512,029
February 20257,505
January 202510,068
December 20249,115
November 20245,510
October 20246,500
September 20247,419
August 20248,979
July 20248,972
June 20248,664
May 202414,153
April 202414,257
March 202413,238
February 20249,864
January 20249,642

Source: EIA Form EIA-923, through August 2026.

How much of Maine's electricity comes from the Anson Abenaki Hydros plant?

Anson Abenaki Hydros made 0.7% of the 14,688,970 MWh reported by Maine plants in 2025, from 0.5% of the state's 6,164 MW of capacity. Its share of output is 1.5 times its share of capacity. By capacity it is the 35th largest of 274 plants in Maine, the 4,430th largest of 14,327 in the U.S. and the 375th largest of 1,393 hydro plants. By 2025 generation it is the 29th largest of 242 generating plants in the state.

Anson Abenaki Hydros within Maine, 2025
MeasureThis plantMaineShare
Capacity (MW)296,1640.5%
Generation (MWh)100,58714,688,9700.7%
Hydro capacity (MW)296724.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Anson Abenaki Hydros plant, and when do they retire?

13 operable generators total 29 MW, with an average age of 44 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 1 has already retired, totalling 3 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1950s139%none reported
1960s139%none reported
1980s102172%none reported
2000s1310%none reported
Every generator, 14 in all
UnitStatusTechnologyMWIn servicePlanned retirement
AB7OperatingConventional Hydroelectric31950n/a
AB5OperatingConventional Hydroelectric31961n/a
AB2OperatingConventional Hydroelectric31980n/a
AB1OperatingConventional Hydroelectric31983n/a
AB3OperatingConventional Hydroelectric31983n/a
AB4OperatingConventional Hydroelectric31983n/a
AN1OperatingConventional Hydroelectric21984n/a
AN2OperatingConventional Hydroelectric21984n/a
AN3OperatingConventional Hydroelectric21984n/a
AN4OperatingConventional Hydroelectric21984n/a
AN5OperatingConventional Hydroelectric21984n/a
AB8OperatingConventional Hydroelectric01989n/a
AB6OperatingConventional Hydroelectric32008n/a
STG1RetiredNatural Gas Steam Turbine319942016

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Anson Abenaki Hydros plant?

Eagle Creek Madison Hydro, LLC is the only joint owner reported for Anson Abenaki Hydros, with 100.0%. Eagle Creek Renewable Energy, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Anson Abenaki Hydros plant?

Anson Abenaki Hydros is in Madison, Somerset County, Maine, at 44.7975° N, 69.8867° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Maine are similar in size?

Maine has 48 operable hydro plants with 672 MW of capacity, and Anson Abenaki Hydros' 29 MW is 4% of that.

Hydro plants in Maine around this size
PlantCountyMW2025 MWh
Rumford Falls Hydro FacilityOxford45214,099
Anson Abenaki HydrosSomerset29100,587
Charles E MontyAndroscoggin28114,402
Brunswick HydroCumberland2069,565
Worumbo Hydro StationAndroscoggin1974,321

Source: EIA Forms EIA-860 and EIA-923, 2025.