Natural gas power plant, Texas

Barney M Davis natural gas power plant, Texas

Barney M Davis is a 1,082 MW natural gas power plant in Nueces County, Texas, operated by City of San Antonio-(TX), and it generated 1,579,099 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Texas, and its capacity factor sits at the 47th percentile of U.S. natural gas plants. By 2025 generation it ranks 583rd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

1,082 MWNameplate capacity
19%Capacity factor, 2025, 47th percentile, on 925 MW net summer
0.3%Of TX generation, 2025
38 yearsAverage generator age, by MW

How hard does the Barney M Davis plant run compared with other natural gas plants?

The Barney M Davis plant had a capacity factor of 19% in 2025 on 925 MW of net summer capacity, the 47th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 71 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Barney M Davis19%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Barney M Davis plant generating more or less than last year?

Barney M Davis generated 1,579,099 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 36.0% ahead of the same months of 2025. 2024 has output for only 11 months, so the two years are not compared.

Net generation by period
PeriodMWh
20241,560,909
20251,579,099
2026 through August1,201,500
2025, same months883,577
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026308,076
July 2026275,757
June 2026236,398
May 2026179,835
April 20261,701
March 202659,631
February 202613,518
January 2026126,584
December 2025119,146
November 202529,712
October 2025301,695
September 2025244,969
August 2025301,962
July 2025141,983
June 2025124,256
May 202553,002
April 20250
March 2025102,408
February 202540,756
January 2025119,210
December 202479,819
November 202439,437
October 2024216,084
September 2024220,671
August 2024377,268
July 202464,338
June 2024228,972
May 2024151,913
April 202450,368
March 20240
February 202450,421
January 202481,618

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Barney M Davis plant?

Barney M Davis made 0.3% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.6% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 29th largest of 1,023 plants in Texas, the 277th largest of 14,327 in the U.S. and the 129th largest of 1,962 natural gas plants. By 2025 generation it is the 86th largest of 816 generating plants in the state.

Barney M Davis within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)1,082195,9660.6%
Generation (MWh)1,579,099592,896,1760.3%
Natural gas capacity (MW)1,08281,5741.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Barney M Davis plant, and when do they retire?

4 operable generators total 1,082 MW, with an average age of 38 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1970s270365%none reported
2010s237935%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingNatural Gas Steam Turbine3521974n/a
2OperatingNatural Gas Fired Combined Cycle3511976n/a
3OperatingNatural Gas Fired Combined Cycle1902010n/a
4OperatingNatural Gas Fired Combined Cycle1902010n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Barney M Davis plant?

EIA lists no joint owners for Barney M Davis. City of San Antonio-(TX) operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does City of San Antonio charge homes?

City of San Antonio, the operator of Barney M Davis, had an average residential price of 12.40¢ per kWh and an average bill of $133 a month in 2025, 19% below the Texas average of 15.40¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Texas
City of San Antonio12.40¢$13319% lower
Texas average15.40¢$171
U.S. average17.23¢$15112% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Barney M Davis plant?

Barney M Davis is in Corpus Christi, Nueces County, Texas, at 27.6064° N, 97.3117° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Texas are similar in size?

Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Barney M Davis' 1,082 MW is 1% of that.

Natural gas plants in Texas around this size
PlantCountyMW2025 MWh
NewmanEl Paso1,1104,003,483
Rio Nogales Power ProjectGuadalupe1,1084,144,257
Guadalupe Generating StationGuadalupe1,0885,712,188
Barney M DavisNueces1,0821,579,099
HarringtonPotter1,0802,018,141
Freestone Energy CenterFreestone1,0366,479,914
Montgomery CountyMontgomery1,0005,870,260

Source: EIA Forms EIA-860 and EIA-923, 2025.