Beaver Dam (AR) is a 112 MW hydro power plant in Carroll County, Arkansas, operated by USCE-Little Rock District, and it generated 184,144 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Arkansas, and its capacity factor sits at the 13th percentile of U.S. hydro plants. By 2025 generation it ranks 2,608th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Beaver Dam (AR) plant run compared with other hydro plants?
The Beaver Dam (AR) plant had a capacity factor of 16% in 2025 on 129 MW of net summer capacity, the 13th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 60 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Beaver Dam (AR) | 16% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Beaver Dam (AR) plant generating more or less than last year?
Generation at Beaver Dam (AR) rose 94.7% from 2024 to 2025, from 94,577 MWh to 184,144 MWh.
| Period | MWh |
|---|---|
| 2024 | 94,577 |
| 2025 | 184,144 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 7,751 |
| November 2025 | 3,426 |
| October 2025 | 9,703 |
| September 2025 | 16,399 |
| August 2025 | 20,655 |
| July 2025 | 13,684 |
| June 2025 | 22,226 |
| May 2025 | 38,098 |
| April 2025 | 24,122 |
| March 2025 | 7,592 |
| February 2025 | 12,503 |
| January 2025 | 7,985 |
| December 2024 | 4,093 |
| November 2024 | 4,155 |
| October 2024 | 7,697 |
| September 2024 | 7,585 |
| August 2024 | 8,979 |
| July 2024 | 12,777 |
| June 2024 | 16,486 |
| May 2024 | 19,300 |
| April 2024 | 5,052 |
| March 2024 | 595 |
| February 2024 | 2,504 |
| January 2024 | 5,354 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Beaver Dam (AR) plant, and when do they retire?
2 operable generators total 112 MW, with an average age of 60 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1960s | 2 | 112 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Out of service, returning | Conventional Hydroelectric | 56 | 1965 | n/a |
| 2 | Operating | Conventional Hydroelectric | 56 | 1965 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Beaver Dam (AR) plant?
EIA lists no joint owners for Beaver Dam (AR). USCE-Little Rock District operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Beaver Dam (AR) plant?
Beaver Dam (AR) is in Eureka Springs, Carroll County, Arkansas, at 36.4215° N, 93.8474° W. It sits in the Southwestern Power Administration balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Arkansas are similar in size?
Arkansas has 19 operable hydro plants with 1,321 MW of capacity, and Beaver Dam (AR)'s 112 MW is 8% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Dardanelle | Pope | 161 | 539,009 |
| Beaver Dam (AR) | Carroll | 112 | 184,144 |
| Dam 2 | Desha | 103 | 385,060 |
| Ozark | Franklin | 100 | 279,583 |
| Greers Ferry Lake | Cleburne | 96 | 241,240 |