Natural gas power plant, California

Berry Placerita Cogen natural gas power plant, California

Berry Placerita Cogen is a 42.8 MW natural gas power plant in Los Angeles County, California, operated by Shadow Wolf Energy, and it generated 3,815 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 10th percentile of U.S. natural gas plants. By 2025 generation it ranks 8,907th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

42.8 MWNameplate capacity
1%Capacity factor, 2025, 10th percentile, on 40 MW net summer
8,907thU.S. rank by generation, 2025
35 yearsAverage generator age, by MW

How hard does the Berry Placerita Cogen plant run compared with other natural gas plants?

The Berry Placerita Cogen plant had a capacity factor of 1% in 2025 on 40 MW of net summer capacity, the 10th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 4 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Berry Placerita Cogen1%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Berry Placerita Cogen plant generating more or less than last year?

Berry Placerita Cogen generated 3,815 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 55.3% ahead of the same months of 2025. 2024 has output for only 8 months, so the two years are not compared.

Net generation by period
PeriodMWh
202429,939
20253,815
2026 through August2,732
2025, same months1,759
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026938
July 2026349
June 2026391
May 2026231
April 2026258
March 2026415
February 2026150
January 20260
December 20251,840
November 20250
October 202598
September 2025118
August 2025164
July 20251,066
June 2025158
May 20250
April 20250
March 202540
February 2025331
January 20250
December 202499
November 202453
October 202444
September 2024514
August 20243,336
July 202410,628
June 202410,043
May 20245,222
April 20240
March 20240
February 20240
January 20240

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Berry Placerita Cogen plant?

Berry Placerita Cogen made 0.0% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 492nd largest of 1,877 plants in California, the 4,025th largest of 14,327 in the U.S. and the 1,143rd largest of 1,962 natural gas plants. By 2025 generation it is the 1,146th largest of 1,608 generating plants in the state.

Berry Placerita Cogen within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)43107,4330.0%
Generation (MWh)3,815204,542,8980.0%
Natural gas capacity (MW)4340,2110.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Berry Placerita Cogen plant, and when do they retire?

2 operable generators total 42.8 MW, with an average age of 35 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1990s243100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingNatural Gas Fired Combustion Turbine211990n/a
GEN2OperatingNatural Gas Fired Combustion Turbine211990n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Berry Placerita Cogen plant?

EIA lists no joint owners for Berry Placerita Cogen. Shadow Wolf Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Berry Placerita Cogen plant?

Berry Placerita Cogen is in Santa Clarita, Los Angeles County, California, at 34.3841° N, 118.4949° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in California are similar in size?

California has 304 operable natural gas plants with 40,211 MW of capacity, and Berry Placerita Cogen's 42.8 MW is 0% of that.

Natural gas plants in California around this size
PlantCountyMW2025 MWh
Live Oak LimitedKern4621,065
Century Generating FacilitySan Bernardino45563
Drews Generating FacilitySan Bernardino45570
Berry Placerita CogenLos Angeles433,815
Springs Generating StationRiverside40878
Mid-Set CogenerationKern39n/a
Salinas River CogenerationMonterey39261,655

Source: EIA Forms EIA-860 and EIA-923, 2025.