Natural gas power plant, California
Blythe Energy Inc natural gas power plant, California
Blythe Energy Inc is a 591 MW natural gas power plant in Riverside County, California, operated by AltaGas Blythe Operations Inc, and it generated 315,228 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in California, and its capacity factor sits at the 29th percentile of U.S. natural gas plants. By 2025 generation it ranks 1,907th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Blythe Energy Inc plant run compared with other natural gas plants?
The Blythe Energy Inc plant had a capacity factor of 7% in 2025 on 514 MW of net summer capacity, the 29th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 26 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Blythe Energy Inc | 7% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Blythe Energy Inc plant generating more or less than last year?
Blythe Energy Inc generated 315,228 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 117.0% ahead of the same months of 2025. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 645,060 |
| 2025 | 315,228 |
| 2026 through August | 338,489 |
| 2025, same months | 155,994 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 165,615 |
| July 2026 | 117,292 |
| June 2026 | 2,575 |
| May 2026 | 15,947 |
| April 2026 | 0 |
| March 2026 | 37,060 |
| February 2026 | 0 |
| January 2026 | 0 |
| December 2025 | 8,297 |
| November 2025 | 20,687 |
| October 2025 | 26,002 |
| September 2025 | 104,248 |
| August 2025 | 74,727 |
| July 2025 | 28,206 |
| June 2025 | 734 |
| May 2025 | 32,908 |
| April 2025 | 3,487 |
| March 2025 | 9,791 |
| February 2025 | 6,141 |
| January 2025 | 0 |
| December 2024 | 7,954 |
| November 2024 | 51,694 |
| October 2024 | 51,895 |
| September 2024 | 60,091 |
| August 2024 | 96,608 |
| July 2024 | 127,618 |
| June 2024 | 39,252 |
| May 2024 | 34,674 |
| April 2024 | 90,923 |
| March 2024 | 14,193 |
| February 2024 | 0 |
| January 2024 | 70,158 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Blythe Energy Inc plant, and when do they retire?
3 operable generators total 591 MW, with an average age of 22 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 3 | 591 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CT1 | Operating | Natural Gas Fired Combined Cycle | 182 | 2003 | n/a |
| CT2 | Operating | Natural Gas Fired Combined Cycle | 182 | 2003 | n/a |
| ST1 | Operating | Natural Gas Fired Combined Cycle | 227 | 2003 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Blythe Energy Inc plant?
EIA lists no joint owners for Blythe Energy Inc. AltaGas Blythe Operations Inc operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Blythe Energy Inc plant?
Blythe Energy Inc is in Blythe, Riverside County, California, at 33.6157° N, 114.6865° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in California are similar in size?
California has 304 operable natural gas plants with 40,211 MW of capacity, and Blythe Energy Inc's 591 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Metcalf Energy Center | Santa Clara | 635 | 2,334,357 |
| Elk Hills Power LLC | Kern | 623 | 3,131,218 |
| Gateway Generating Station | Contra Costa | 620 | 2,911,928 |
| Blythe Energy Inc | Riverside | 591 | 315,228 |
| Palomar Energy | San Diego | 559 | 1,469,615 |
| Cosumnes Power Plant | Sacramento | 557 | 3,500,786 |
| Harbor | Los Angeles | 548 | 89,429 |
Source: EIA Forms EIA-860 and EIA-923, 2025.