Skip to main content
RateWatt

Solar power plant, Florida

Buttonwood solar power plant, Florida

Buttonwood is a 74.5 MW solar power plant in St Lucie County, Florida, operated by Florida Power & Light Co, and it generated 194,396 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Florida, and its capacity factor sits at the 90th percentile of U.S. solar plants. By 2025 generation it ranks 2,537th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

74.5 MWNameplate capacity
30%Capacity factor, 2025, 90th percentile, on 74.5 MW net summer
0.1%Of FL generation, 2025
1 yearAverage generator age, by MW

How hard does the Buttonwood plant run compared with other solar plants?

The Buttonwood plant had a capacity factor of 30% in 2025 on 74.5 MW of net summer capacity, the 90th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 109 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Buttonwood30%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Buttonwood plant generating more or less than last year?

Buttonwood generated 194,396 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 4.3% behind the same months of 2025. 2024 has output for only 2 months, so the two years are not compared.

Net generation by period
PeriodMWh
202420,779
2025194,396
2026 through August131,636
2025, same months137,547
Monthly generation, Nov 2024 to Aug 2026
MonthMWh
August 202616,527
July 202617,727
June 202617,779
May 202618,732
April 202617,374
March 202616,373
February 202614,377
January 202612,747
December 202512,694
November 202514,138
October 202515,129
September 202514,888
August 202517,824
July 202518,177
June 202518,282
May 202518,898
April 202520,541
March 202519,153
February 202513,930
January 202510,742
December 202411,709
November 20249,070

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Buttonwood plant?

Buttonwood made 0.1% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.1% of the state's 79,936 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 105th largest of 331 plants in Florida, the 3,163rd largest of 14,327 in the U.S. and the 731st largest of 7,223 solar plants. By 2025 generation it is the 69th largest of 313 generating plants in the state.

Buttonwood within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)7579,9360.1%
Generation (MWh)194,396267,867,7350.1%
Solar capacity (MW)7512,2230.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Buttonwood plant, and when do they retire?

1 operable generator totals 74.5 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s175100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingSolar Photovoltaic752024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Buttonwood plant?

EIA lists no joint owners for Buttonwood. Florida Power & Light Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Florida Power & Light Co charge homes?

Florida Power & Light Co, the operator of Buttonwood, had an average residential price of 14.62¢ per kWh and an average bill of $162 a month in 2025, 4% below the Florida average of 15.21¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Florida
Florida Power & Light Co14.62¢$1624% lower
Florida average15.21¢$168
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Buttonwood plant?

Buttonwood is in Fort Pierce, St Lucie County, Florida, at 27.5503° N, 80.6711° W. It sits in the Florida Power & Light Company balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Florida are similar in size?

Florida has 210 operable solar plants with 12,223 MW of capacity, and Buttonwood's 74.5 MW is 1% of that.

Solar plants in Florida around this size
PlantCountyMW2025 MWh
Thomas CreekNassau75160,457
Green PastureCharlotte75188,554
FawnMartin75187,470
ButtonwoodSt Lucie75194,396
HoneybellOkeechobee75194,848
HolopawPalm Beach75182,747
Nature TrailBaker75189,167

Source: EIA Forms EIA-860 and EIA-923, 2025.