Hydro power plant, Georgia

Carters hydroelectric power plant, Georgia

Carters is a 500 MW power plant, 250 MW of it hydro, in Murray County, Georgia, operated by USCE-Mobile District, and it generated 30,171 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 8th percentile of U.S. hydro plants. By 2025 generation it ranks 4,742nd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

500 MWNameplate capacity
13%Capacity factor, 2025, hydro units, 8th percentile, on 240 MW net summer
4,742ndU.S. rank by generation, 2025
49 yearsAverage generator age, by MW

How hard does the Carters plant run compared with other hydro plants?

The Carters plant's hydro units had a capacity factor of 13% in 2025 on 240 MW of net summer capacity, the 8th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 47 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Carters13%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its hydro generators only. Values above 105% are left out of the comparison.

Is the Carters plant generating more or less than last year?

Carters generated 30,171 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 167.3% behind the same months of 2025. 2024 has output for only 7 months, so the two years are not compared.

18 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.

Net generation by period
PeriodMWh
202430,076
202530,171
2026 through August-40,543
2025, same months60,243
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026-7,483
July 2026-10,235
June 2026-4,158
May 2026-9,638
April 2026-5,268
March 20264,043
February 2026-2,204
January 2026-5,600
December 2025-3,609
November 2025-9,517
October 2025-9,979
September 2025-6,967
August 2025-6,893
July 2025-3,557
June 20259,201
May 202518,761
April 202516,203
March 202511,000
February 202510,219
January 20255,309
December 20242,012
November 2024-5,509
October 2024320
September 2024-8,852
August 2024-13,814
July 2024-2,353
June 2024-122
May 202422,429
April 20248,159
March 202415,687
February 20249,033
January 20243,086

Source: EIA Form EIA-923, through August 2026.

How much of Georgia's electricity comes from the Carters plant?

Carters made 0.0% of the 144,967,352 MWh reported by Georgia plants in 2025, from 1.2% of the state's 42,719 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 24th largest of 263 plants in Georgia, the 733rd largest of 14,327 in the U.S. and the 57th largest of 1,393 hydro plants on its hydro units alone. By 2025 generation it is the 125th largest of 242 generating plants in the state.

Carters within Georgia, 2025
MeasureThis plantGeorgiaShare
Capacity (MW)50042,7191.2%
Generation (MWh)30,171144,967,3520.0%
Hydro capacity (MW)2501,55016.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Carters plant, and when do they retire?

4 operable generators total 500 MW, with an average age of 49 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1970s4500100%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric1251975n/a
2OperatingConventional Hydroelectric1251975n/a
3OperatingHydroelectric Pumped Storage1251977n/a
4OperatingHydroelectric Pumped Storage1251977n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Carters plant?

EIA lists no joint owners for Carters. USCE-Mobile District operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What fuels does the Carters plant use?

Carters has capacity on 2 fuels: 50% hydro and 50% battery and pumped storage. In 2025, hydro made 893% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Hydro25050.0%269,344
Battery and pumped storage25050.0%-239,173

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Carters plant?

Carters is in Chatsworth, Murray County, Georgia, at 34.6121° N, 84.6733° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Georgia are similar in size?

Georgia has 27 operable hydro plants with 1,550 MW of capacity, and Carters' 250 MW is 16% of that.

Hydro plants in Georgia around this size
PlantCountyMW2025 MWh
Hartwell LakeHart420344,271
CartersMurray250269,344
Walter F GeorgeClay168340,701
BufordForsyth131142,644

Source: EIA Forms EIA-860 and EIA-923, 2025.