Solar power plant, Utah
Copperton Solar Plant No. 1 power plant, Utah
Copperton Solar Plant No. 1 is a 30 MW solar power plant in Salt Lake County, Utah, operated by Kennecott Utah Copper, and it generated 7,306 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 3rd percentile of U.S. solar plants. By 2025 generation it ranks 7,138th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Copperton Solar Plant No. 1 plant run compared with other solar plants?
The Copperton Solar Plant No. 1 plant had a capacity factor of 3% in 2025 on 29.6 MW of net summer capacity, the 3rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 10 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Copperton Solar Plant No. 1 | 3% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Copperton Solar Plant No. 1 plant generating more or less than last year?
Copperton Solar Plant No. 1 generated 7,306 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 3 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 648 |
| 2025 | 7,306 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 378 |
| November 2025 | 284 |
| October 2025 | 554 |
| September 2025 | 859 |
| August 2025 | 1,061 |
| July 2025 | 1,149 |
| June 2025 | 350 |
| May 2025 | 79 |
| April 2025 | 785 |
| March 2025 | 801 |
| February 2025 | 511 |
| January 2025 | 495 |
| December 2024 | 324 |
| November 2024 | 322 |
| October 2024 | 2 |
| September 2024 | 0 |
| August 2024 | 0 |
| July 2024 | 0 |
| June 2024 | 0 |
| May 2024 | 0 |
| April 2024 | 0 |
| March 2024 | 0 |
| February 2024 | 0 |
| January 2024 | 0 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Copperton Solar Plant No. 1 plant, and when do they retire?
2 operable generators total 30 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 2 | 30 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CSP1 | Operating | Solar Photovoltaic | 5 | 2024 | n/a |
| CSP2 | Operating | Solar Photovoltaic | 25 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Copperton Solar Plant No. 1 plant?
EIA lists no joint owners for Copperton Solar Plant No. 1. Kennecott Utah Copper operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Copperton Solar Plant No. 1 plant?
Copperton Solar Plant No. 1 is in Bingham Canyon, Salt Lake County, Utah, at 40.5766° N, 112.0846° W. It sits in the PacifiCorp - East balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Utah are similar in size?
Utah has 55 operable solar plants with 3,037 MW of capacity, and Copperton Solar Plant No. 1's 30 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Pavant Solar, LLC | Millard | 50 | 114,348 |
| Pavant Solar II LLC | Millard | 50 | 85,894 |
| Castle Solar, LLC | Emery | 40 | 107,994 |
| Copperton Solar Plant No. 1 | Salt Lake | 30 | 7,306 |
| Pavant Solar III | Millard | 20 | 44,205 |
Source: EIA Forms EIA-860 and EIA-923, 2025.