Biomass power plant, Virginia
Covanta Alexandria/Arlington Energy biomass power plant, Virginia
Covanta Alexandria/Arlington Energy is a 29 MW biomass power plant in Alexandria City, Virginia, operated by Covanta Alexandria/Arlington, and it generated 147,340 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Virginia, and its capacity factor sits at the 13th percentile of U.S. biomass plants. By 2025 generation it ranks 2,927th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Covanta Alexandria/Arlington Energy plant run compared with other biomass plants?
The Covanta Alexandria/Arlington Energy plant had a capacity factor of 26% in 2025 on 29 MW of net summer capacity, the 13th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 95 days at full output out of 365.
0%Shaded: the middle half of biomass plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Covanta Alexandria/Arlington Energy | 26% |
| Biomass plants, 75th percentile | 65% |
| Biomass plants, median | 48% |
| Biomass plants, 25th percentile | 35% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Covanta Alexandria/Arlington Energy plant generating more or less than last year?
Generation at Covanta Alexandria/Arlington Energy rose 3.8% from 2024 to 2025, from 141,908 MWh to 147,340 MWh. Through August 2026 it is running 1.8% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 141,908 |
| 2025 | 147,340 |
| 2026 through August | 96,297 |
| 2025, same months | 98,112 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 11,999 |
| July 2026 | 11,828 |
| June 2026 | 12,462 |
| May 2026 | 12,647 |
| April 2026 | 12,798 |
| March 2026 | 12,556 |
| February 2026 | 10,483 |
| January 2026 | 11,524 |
| December 2025 | 13,317 |
| November 2025 | 12,961 |
| October 2025 | 10,875 |
| September 2025 | 12,075 |
| August 2025 | 12,991 |
| July 2025 | 10,694 |
| June 2025 | 11,906 |
| May 2025 | 12,563 |
| April 2025 | 13,882 |
| March 2025 | 13,553 |
| February 2025 | 10,531 |
| January 2025 | 11,992 |
| December 2024 | 12,171 |
| November 2024 | 12,955 |
| October 2024 | 10,699 |
| September 2024 | 11,015 |
| August 2024 | 13,154 |
| July 2024 | 11,311 |
| June 2024 | 11,345 |
| May 2024 | 12,286 |
| April 2024 | 12,668 |
| March 2024 | 12,629 |
| February 2024 | 10,098 |
| January 2024 | 11,577 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Covanta Alexandria/Arlington Energy plant, and when do they retire?
2 operable generators total 29 MW, with an average age of 38 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 2 | 29 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Municipal Solid Waste | 15 | 1987 | n/a |
| GEN2 | Operating | Municipal Solid Waste | 15 | 1987 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Covanta Alexandria/Arlington Energy plant?
EIA lists no joint owners for Covanta Alexandria/Arlington Energy. Covanta Alexandria/Arlington operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Covanta Alexandria/Arlington Energy plant?
Covanta Alexandria/Arlington Energy is in Alexandria, Alexandria City, Virginia, at 38.8014° N, 77.1288° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which biomass plants in Virginia are similar in size?
Virginia has 24 operable biomass plants with 816 MW of capacity, and Covanta Alexandria/Arlington Energy's 29 MW is 4% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Halifax County Biomass | Halifax | 50 | 358,696 |
| Hopewell Mill | Hopewell City | 48 | 220,745 |
| International Paper Franklin Mill | Isle of Wight | 36 | 225,632 |
| Covanta Alexandria/Arlington Energy | Alexandria City | 29 | 66,303 |
Source: EIA Forms EIA-860 and EIA-923, 2025.