Petroleum power plant, Maryland
Easton 2 petroleum power plant, Maryland
Easton 2 is a 38.8 MW petroleum power plant in Talbot County, Maryland, operated by Easton Utilities Comm, and it generated 4,367 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 73rd percentile of U.S. petroleum plants. By 2025 generation it ranks 8,422nd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Easton 2 plant run compared with other petroleum plants?
The Easton 2 plant had a capacity factor of 1% in 2025 on 37 MW of net summer capacity, the 73rd percentile of the 143 U.S. petroleum plants with at least 20 MW. The typical petroleum plant reached 1%. That equals about 5 days at full output out of 365.
0%Shaded: the middle half of petroleum plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Easton 2 | 1% |
| Petroleum plants, 75th percentile | 1% |
| Petroleum plants, median | 1% |
| Petroleum plants, 25th percentile | 0% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Easton 2 plant generating more or less than last year?
Easton 2 generated 4,367 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 49.5% ahead of the same months of 2025. 2024 has output for only 3 months, so the two years are not compared.
13 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.
| Period | MWh |
|---|---|
| 2024 | -674 |
| 2025 | 4,367 |
| 2026 through August | 4,526 |
| 2025, same months | 3,028 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 20 |
| July 2026 | 454 |
| June 2026 | 191 |
| May 2026 | 135 |
| April 2026 | 13 |
| March 2026 | 0 |
| February 2026 | 1,268 |
| January 2026 | 2,445 |
| December 2025 | 1,489 |
| November 2025 | -110 |
| October 2025 | -40 |
| September 2025 | 0 |
| August 2025 | 57 |
| July 2025 | 729 |
| June 2025 | 634 |
| May 2025 | 0 |
| April 2025 | 203 |
| March 2025 | 1,480 |
| February 2025 | -10 |
| January 2025 | -65 |
| December 2024 | -137 |
| November 2024 | -78 |
| October 2024 | -88 |
| September 2024 | -91 |
| August 2024 | -76 |
| July 2024 | 142 |
| June 2024 | 7 |
| May 2024 | -77 |
| April 2024 | -86 |
| March 2024 | -110 |
| February 2024 | -89 |
| January 2024 | 9 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Easton 2 plant, and when do they retire?
8 operable generators total 38.8 MW, with an average age of 35 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 2 | 12 | 32% | none reported |
| 1980s | 2 | 13 | 32% | none reported |
| 1990s | 2 | 3 | 8% | none reported |
| 2000s | 2 | 11 | 28% | none reported |
Every generator, 8 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 21 | Operating | Petroleum Liquids | 6 | 1978 | n/a |
| 22 | Operating | Petroleum Liquids | 6 | 1978 | n/a |
| 23 | Operating | Petroleum Liquids | 6 | 1989 | n/a |
| 24 | Operating | Petroleum Liquids | 6 | 1989 | n/a |
| 201 | Operating | Petroleum Liquids | 2 | 1995 | n/a |
| 202 | Operating | Petroleum Liquids | 2 | 1995 | n/a |
| 203 | Operating | Petroleum Liquids | 5 | 2004 | n/a |
| 204 | Operating | Petroleum Liquids | 5 | 2004 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Easton 2 plant?
EIA lists no joint owners for Easton 2. Easton Utilities Comm operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Easton Utilities Comm charge homes?
Easton Utilities Comm, the operator of Easton 2, had an average residential price of 15.18¢ per kWh and an average bill of $159 a month in 2025, 22% below the Maryland average of 19.53¢.
| Measure | Price | Monthly bill | Against Maryland |
|---|---|---|---|
| Easton Utilities Comm | 15.18¢ | $159 | 22% lower |
| Maryland average | 19.53¢ | $184 | |
| U.S. average | 17.23¢ | $151 | 12% lower |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Easton 2 plant?
Easton 2 is in Easton, Talbot County, Maryland, at 38.7950° N, 76.0700° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which petroleum plants in Maryland are similar in size?
Maryland has 10 operable petroleum plants with 1,478 MW of capacity, and Easton 2's 38.8 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Easton 2 | Talbot | 39 | 4,367 |
| Easton | Talbot | 31 | 2,704 |
Source: EIA Forms EIA-860 and EIA-923, 2025.