Echo Wind Park power plant, Michigan

Echo Wind Park is a 162 MW wind power plant in Huron County, Michigan, operated by DTE Electric Company, and it generated 574,571 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Michigan, and its capacity factor sits at the 74th percentile of U.S. wind plants. By 2025 generation it ranks 1,176th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

162 MWNameplate capacity
40%Capacity factor, 2025, 74th percentile, on 162 MW net summer
0.4%Of MI generation, 2025
10 yearsAverage generator age, by MW

How hard does the Echo Wind Park plant run compared with other wind plants?

The Echo Wind Park plant had a capacity factor of 40% in 2025 on 162 MW of net summer capacity, the 74th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 148 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Echo Wind Park40%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Echo Wind Park plant generating more or less than last year?

Generation at Echo Wind Park rose 8.6% from 2024 to 2025, from 528,853 MWh to 574,571 MWh. Through August 2026 it is running 3.8% behind the same months of 2025.

Net generation by period
PeriodMWh
2024528,853
2025574,571
2026 through August367,948
2025, same months382,425
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202624,341
July 202625,239
June 202633,858
May 202649,757
April 202653,428
March 202659,738
February 202648,438
January 202673,149
December 202564,519
November 202563,880
October 202543,198
September 202520,549
August 202528,086
July 202523,140
June 202537,843
May 202546,581
April 202554,517
March 202565,237
February 202551,199
January 202575,822
December 202463,029
November 202460,162
October 202456,654
September 202431,878
August 202424,576
July 202419,175
June 202437,555
May 202437,942
April 202460,556
March 202464,133
February 202434,697
January 202438,496

Source: EIA Form EIA-923, through August 2026.

How much of Michigan's electricity comes from the Echo Wind Park plant?

Echo Wind Park made 0.4% of the 127,929,498 MWh reported by Michigan plants in 2025, from 0.5% of the state's 34,725 MW of capacity. By capacity it is the 30th largest of 283 plants in Michigan, the 1,877th largest of 14,327 in the U.S. and the 405th largest of 1,358 wind plants. By 2025 generation it is the 22nd largest of 261 generating plants in the state.

Echo Wind Park within Michigan, 2025
MeasureThis plantMichiganShare
Capacity (MW)16234,7250.5%
Generation (MWh)574,571127,929,4980.4%
Wind capacity (MW)1623,7774.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Echo Wind Park plant, and when do they retire?

3 operable generators total 162 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s3162100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingOnshore Wind Turbine502014n/a
GEN2OperatingOnshore Wind Turbine622014n/a
GEN3OperatingOnshore Wind Turbine502016n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Echo Wind Park plant?

EIA lists no joint owners for Echo Wind Park. DTE Electric Company operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does DTE Electric Company charge homes?

DTE Electric Company, the operator of Echo Wind Park, had an average residential price of 20.25¢ per kWh and an average bill of $126 a month in 2025, 1% above the Michigan average of 20.03¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Michigan
DTE Electric Company20.25¢$1261% higher
Michigan average20.03¢$127
U.S. average17.23¢$15114% lower

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Echo Wind Park plant?

Echo Wind Park is in Elkton, Huron County, Michigan, at 43.8825° N, 83.1614° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region RFC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Michigan are similar in size?

Michigan has 34 operable wind plants with 3,777 MW of capacity, and Echo Wind Park's 162 MW is 4% of that.

Wind plants in Michigan around this size
PlantCountyMW2025 MWh
Heartland FarmsGratiot200469,867
Pegasus WindTuscola178386,770
Polaris Wind ParkGratiot169454,620
Echo Wind ParkHuron162574,571
Pine River Wind ParkIsabella161380,627
Crescent Wind ParkHillsdale150362,063
Gratiot Farms Wind ProjectMontcalm150344,468

Source: EIA Forms EIA-860 and EIA-923, 2025.