Solar power plant, Pennsylvania
Elk Hill Solar 1 power plant, Pennsylvania
Elk Hill Solar 1 is a 20 MW solar power plant in Franklin County, Pennsylvania, operated by Lightsource Renewable Energy Asset Management, LLC, and it generated 34,681 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 24th percentile of U.S. solar plants. By 2025 generation it ranks 4,552nd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Elk Hill Solar 1 plant run compared with other solar plants?
The Elk Hill Solar 1 plant had a capacity factor of 20% in 2025 on 20 MW of net summer capacity, the 24th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 72 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Elk Hill Solar 1 | 20% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Elk Hill Solar 1 plant generating more or less than last year?
Generation at Elk Hill Solar 1 fell 9.7% from 2024 to 2025, from 38,391 MWh to 34,681 MWh.
| Period | MWh |
|---|---|
| 2024 | 38,391 |
| 2025 | 34,681 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,292 |
| November 2025 | 1,757 |
| October 2025 | 2,771 |
| September 2025 | 3,040 |
| August 2025 | 3,816 |
| July 2025 | 3,498 |
| June 2025 | 3,587 |
| May 2025 | 3,536 |
| April 2025 | 3,542 |
| March 2025 | 3,698 |
| February 2025 | 2,157 |
| January 2025 | 1,987 |
| December 2024 | 1,302 |
| November 2024 | 2,033 |
| October 2024 | 3,504 |
| September 2024 | 3,196 |
| August 2024 | 4,023 |
| July 2024 | 4,323 |
| June 2024 | 4,791 |
| May 2024 | 3,829 |
| April 2024 | 3,622 |
| March 2024 | 3,553 |
| February 2024 | 2,758 |
| January 2024 | 1,457 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Elk Hill Solar 1 plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| PAEH1 | Operating | Solar Photovoltaic | 20 | 2022 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Elk Hill Solar 1 plant?
Elk Hill Solar 1, LLC is the only joint owner reported for Elk Hill Solar 1, with 100.0%. Lightsource Renewable Energy Asset Management, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Elk Hill Solar 1 plant?
Elk Hill Solar 1 is in Mercersburg, Franklin County, Pennsylvania, at 39.8492° N, 77.9291° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Pennsylvania are similar in size?
Pennsylvania has 74 operable solar plants with 1,131 MW of capacity, and Elk Hill Solar 1's 20 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Whitetail Solar 2 | Franklin | 20 | 34,798 |
| Whitetail Solar 3 | Franklin | 20 | 33,432 |
| Elk Hill Solar 1 | Franklin | 20 | 34,681 |
| CL-Viaduct LLC | Clearfield | 20 | 30,496 |
| UN-School House LLC | Clearfield | 20 | 29,143 |
| Cottontail Solar 1 | York | 20 | 31,878 |