Skip to main content
RateWatt

Petroleum power plant, Kansas

Erie Energy Center, Kansas

Erie Energy Center is a 20 MW petroleum power plant in Neosho County, Kansas, operated by City of Erie-(KS), and it generated 2,430 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 74th percentile of U.S. petroleum plants. By 2025 generation it ranks 10,225th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

20 MWNameplate capacity
1%Capacity factor, 2025, 74th percentile, on 20 MW net summer
10,225thU.S. rank by generation, 2025
26 yearsAverage generator age, by MW

How hard does the Erie Energy Center plant run compared with other petroleum plants?

The Erie Energy Center plant had a capacity factor of 1% in 2025 on 20 MW of net summer capacity, the 74th percentile of the 143 U.S. petroleum plants with at least 20 MW. The typical petroleum plant reached 1%. That equals about 5 days at full output out of 365.

0%Shaded: the middle half of petroleum plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Erie Energy Center1%
Petroleum plants, 75th percentile1%
Petroleum plants, median1%
Petroleum plants, 25th percentile0%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Erie Energy Center plant generating more or less than last year?

Generation at Erie Energy Center rose 77.1% from 2024 to 2025, from 1,372 MWh to 2,430 MWh.

Net generation by period
PeriodMWh
20241,372
20252,430
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 2025267
November 2025165
October 2025179
September 2025176
August 2025199
July 2025169
June 2025274
May 202596
April 2025168
March 2025223
February 2025231
January 2025283
December 2024100
November 2024107
October 2024110
September 202473
August 202497
July 202480
June 202481
May 2024118
April 202497
March 2024121
February 2024152
January 2024237

Source: EIA Form EIA-923, through August 2026.

How much of Kansas' electricity comes from the Erie Energy Center plant?

Erie Energy Center made 0.0% of the 61,984,540 MWh reported by Kansas plants in 2025, from 0.1% of the state's 20,969 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 89th largest of 190 plants in Kansas, the 4,775th largest of 14,327 in the U.S. and the 178th largest of 861 petroleum plants. By 2025 generation it is the 99th largest of 173 generating plants in the state.

Erie Energy Center within Kansas, 2025
MeasureThis plantKansasShare
Capacity (MW)2020,9690.1%
Generation (MWh)2,43061,984,5400.0%
Petroleum capacity (MW)204604.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Erie Energy Center plant, and when do they retire?

8 operable generators total 20 MW, with an average age of 26 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1990s820100%none reported
Every generator, 8 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingPetroleum Liquids31999n/a
2OperatingPetroleum Liquids31999n/a
3OperatingPetroleum Liquids31999n/a
4OperatingPetroleum Liquids31999n/a
5OperatingPetroleum Liquids31999n/a
6OperatingPetroleum Liquids31999n/a
7OperatingPetroleum Liquids31999n/a
8OperatingPetroleum Liquids31999n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Erie Energy Center plant?

EIA lists no joint owners for Erie Energy Center. City of Erie-(KS) operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does City of Erie charge homes?

City of Erie, the operator of Erie Energy Center, had an average residential price of 16.68¢ per kWh and an average bill of $126 a month in 2019, 16% above the Kansas average of 14.44¢.

Average residential price and bill, 2019
MeasurePriceMonthly billAgainst Kansas
City of Erie16.68¢$12616% higher
Kansas average14.44¢$126
U.S. average17.23¢$15119% higher

Source: EIA Form EIA-861, final 2019. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Erie Energy Center plant?

Erie Energy Center is in Erie, Neosho County, Kansas, at 37.5742° N, 95.2372° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which petroleum plants in Kansas are similar in size?

Kansas has 37 operable petroleum plants with 460 MW of capacity, and Erie Energy Center's 20 MW is 4% of that.

Petroleum plants in Kansas around this size
PlantCountyMW2025 MWh
Clay CenterClay22-531
Colby City ofThomas210
Erie Energy CenterNeosho202,430
SharpeCoffey20-147
IolaAllen19141
Hugoton 2Stevens1873

Source: EIA Forms EIA-860 and EIA-923, 2025.