Natural gas power plant, California
Fresno Cogen Partners natural gas power plant, California
Fresno Cogen Partners is a 86.8 MW power plant, 70.8 MW of it natural gas, in Fresno County, California, operated by Wellhead Services, Inc, and it generated 840 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 3rd percentile of U.S. natural gas plants. By 2025 generation it ranks 11,940th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Fresno Cogen Partners plant run compared with other natural gas plants?
The Fresno Cogen Partners plant's natural gas units had a capacity factor of under 1% in 2025 on 70.8 MW of net summer capacity, the 3rd percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. It ran for only a few hours of the year at full output.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Fresno Cogen Partners | under 1% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its natural gas generators only. Values above 105% are left out of the comparison.
Is the Fresno Cogen Partners plant generating more or less than last year?
Generation at Fresno Cogen Partners fell 64.9% from 2024 to 2025, from 2,392 MWh to 840 MWh.
| Period | MWh |
|---|---|
| 2024 | 2,392 |
| 2025 | 840 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 50 |
| November 2025 | 86 |
| October 2025 | 73 |
| September 2025 | 106 |
| August 2025 | 147 |
| July 2025 | 89 |
| June 2025 | 52 |
| May 2025 | 24 |
| April 2025 | 19 |
| March 2025 | 35 |
| February 2025 | 62 |
| January 2025 | 96 |
| December 2024 | 221 |
| November 2024 | 191 |
| October 2024 | 245 |
| September 2024 | 238 |
| August 2024 | 264 |
| July 2024 | 314 |
| June 2024 | 151 |
| May 2024 | 60 |
| April 2024 | 80 |
| March 2024 | 125 |
| February 2024 | 201 |
| January 2024 | 303 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Fresno Cogen Partners plant, and when do they retire?
3 operable generators total 86.8 MW, with an average age of 18 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 2 have already retired, totalling 32.3 MW.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 2 | 71 | 82% | none reported |
| 2020s | 1 | 16 | 18% | none reported |
Every generator, 5 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN3 | Operating | Natural Gas Fired Combustion Turbine | 19 | 2001 | n/a |
| GEN4 | Operating | Natural Gas Fired Combustion Turbine | 52 | 2004 | n/a |
| BESS1 | Operating | Batteries | 16 | 2023 | n/a |
| GEN1 | Retired | Natural Gas Fired Combined Cycle | 22 | 1990 | 2004 |
| GEN2 | Retired | Natural Gas Fired Combined Cycle | 10 | 1990 | 2021 |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Fresno Cogen Partners plant?
2 owners report shares in Fresno Cogen Partners; Fresno Power Investors LP holds the largest named share, 61.2% or about 53.1 MW. Wellhead Services, Inc operates the plant. The listed shares add up to 81.6% of capacity; generators without joint owners are not on this list.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| Fresno Power Investors LP | 61.2% | 53 | 514 |
| Fresno Cogen Inc | 20.4% | 18 | 171 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
What fuels does the Fresno Cogen Partners plant use?
Fresno Cogen Partners has capacity on 2 fuels: 82% natural gas and 18% battery and pumped storage. In 2025, natural gas made 188% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Natural gas | 71 | 81.6% | 1,581 |
| Battery and pumped storage | 16 | 18.4% | -741 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Fresno Cogen Partners plant?
Fresno Cogen Partners is in San Joaquin, Fresno County, California, at 36.6170° N, 120.0998° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in California are similar in size?
California has 304 operable natural gas plants with 40,211 MW of capacity, and Fresno Cogen Partners' 70.8 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Martinez Refining | Contra Costa | 80 | 709,913 |
| McClellan (CA) | Sacramento | 77 | 1,236 |
| McClure | Stanislaus | 71 | 1,111 |
| Fresno Cogen Partners | Fresno | 71 | 1,581 |
| Greenleaf 1 | Sutter | 70 | 2,626 |
| Oxnard | Ventura | 69 | 482,033 |
| Roseville Power Plant #2 | Placer | 66 | 568 |
Source: EIA Forms EIA-860 and EIA-923, 2025.