Biomass power plant, Mississippi
GCF US Holdings LLC Columbus Mill biomass power plant, Mississippi
GCF US Holdings LLC Columbus Mill is a 129 MW biomass power plant in Lowndes County, Mississippi, operated by GCF-Columbus Mill, and it generated 506,495 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.7% of the generation reported in Mississippi, and its capacity factor sits at the 36th percentile of U.S. biomass plants. By 2025 generation it ranks 1,324th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the GCF US Holdings LLC Columbus Mill plant run compared with other biomass plants?
The GCF US Holdings LLC Columbus Mill plant had a capacity factor of 40% in 2025 on 129 MW of net summer capacity, the 36th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 146 days at full output out of 365.
0%Shaded: the middle half of biomass plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| GCF US Holdings LLC Columbus Mill | 40% |
| Biomass plants, 75th percentile | 65% |
| Biomass plants, median | 48% |
| Biomass plants, 25th percentile | 35% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the GCF US Holdings LLC Columbus Mill plant generating more or less than last year?
Generation at GCF US Holdings LLC Columbus Mill rose 17.8% from 2024 to 2025, from 429,990 MWh to 506,495 MWh. Through August 2026 it is running 9.5% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 429,990 |
| 2025 | 506,495 |
| 2026 through August | 344,414 |
| 2025, same months | 314,433 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 48,034 |
| July 2026 | 47,360 |
| June 2026 | 45,323 |
| May 2026 | 36,018 |
| April 2026 | 16,879 |
| March 2026 | 49,423 |
| February 2026 | 47,611 |
| January 2026 | 53,766 |
| December 2025 | 47,407 |
| November 2025 | 55,949 |
| October 2025 | 44,787 |
| September 2025 | 43,919 |
| August 2025 | 42,420 |
| July 2025 | 46,378 |
| June 2025 | 37,411 |
| May 2025 | 33,652 |
| April 2025 | 15,895 |
| March 2025 | 47,048 |
| February 2025 | 40,937 |
| January 2025 | 50,692 |
| December 2024 | 38,151 |
| November 2024 | 35,776 |
| October 2024 | 33,115 |
| September 2024 | 40,464 |
| August 2024 | 32,663 |
| July 2024 | 32,471 |
| June 2024 | 34,587 |
| May 2024 | 36,973 |
| April 2024 | 35,855 |
| March 2024 | 36,014 |
| February 2024 | 36,311 |
| January 2024 | 37,610 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the GCF US Holdings LLC Columbus Mill plant, and when do they retire?
4 operable generators total 129 MW, with an average age of 39 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 3 | 65 | 50% | none reported |
| 1990s | 1 | 64 | 50% | none reported |
Every generator, 4 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| TG2 | Operating | Wood/Wood Waste Biomass | 46 | 1982 | n/a |
| TG3 | Operating | Wood/Wood Waste Biomass | 15 | 1982 | n/a |
| TG4 | On standby | Wood/Wood Waste Biomass | 4 | 1987 | n/a |
| TG1 | Operating | Wood/Wood Waste Biomass | 64 | 1990 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the GCF US Holdings LLC Columbus Mill plant?
EIA lists no joint owners for GCF US Holdings LLC Columbus Mill. GCF-Columbus Mill operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the GCF US Holdings LLC Columbus Mill plant?
GCF US Holdings LLC Columbus Mill is in Columbus, Lowndes County, Mississippi, at 33.3602° N, 88.4600° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which biomass plants in Mississippi are similar in size?
Mississippi has 5 operable biomass plants with 313 MW of capacity, and GCF US Holdings LLC Columbus Mill's 129 MW is 41% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| GCF US Holdings LLC Columbus Mill | Lowndes | 129 | 450,109 |
| Georgia-Pacific Monticello Paper | Lawrence | 82 | 342,938 |
Source: EIA Forms EIA-860 and EIA-923, 2025.