Skip to main content
RateWatt

Natural gas power plant, Mississippi

Gerald Andrus natural gas power plant, Mississippi

Gerald Andrus is a 781 MW natural gas power plant in Washington County, Mississippi, operated by Entergy Mississippi LLC, and it generated 566,837 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.7% of the generation reported in Mississippi, and its capacity factor sits at the 34th percentile of U.S. natural gas plants. By 2025 generation it ranks 1,194th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

781 MWNameplate capacity
9%Capacity factor, 2025, 34th percentile, on 701 MW net summer
0.7%Of MS generation, 2025
50 yearsAverage generator age, by MW

How hard does the Gerald Andrus plant run compared with other natural gas plants?

The Gerald Andrus plant had a capacity factor of 9% in 2025 on 701 MW of net summer capacity, the 34th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 34 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Gerald Andrus9%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Gerald Andrus plant generating more or less than last year?

Gerald Andrus generated 566,837 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 5 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024388,516
2025566,837
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20250
November 202523,507
October 202562,331
September 202535,496
August 202592,367
July 2025131,444
June 202578,365
May 2025120,688
April 20250
March 20250
February 202522,639
January 20250
December 20240
November 20240
October 20240
September 20240
August 2024112,296
July 202437,416
June 20240
May 2024194,792
April 20240
March 20245,965
February 20240
January 202438,047

Source: EIA Form EIA-923, through August 2026.

How much of Mississippi's electricity comes from the Gerald Andrus plant?

Gerald Andrus made 0.7% of the 77,727,245 MWh reported by Mississippi plants in 2025, from 4.4% of the state's 17,862 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 11th largest of 63 plants in Mississippi, the 427th largest of 14,327 in the U.S. and the 238th largest of 1,962 natural gas plants. By 2025 generation it is the 17th largest of 57 generating plants in the state.

Gerald Andrus within Mississippi, 2025
MeasureThis plantMississippiShare
Capacity (MW)78117,8624.4%
Generation (MWh)566,83777,727,2450.7%
Natural gas capacity (MW)78112,6786.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Gerald Andrus plant, and when do they retire?

1 operable generator totals 781 MW, with an average age of 50 years weighted by capacity at the end of 2025. 781 MW, 100% of operable capacity, has a planned retirement, the first in 2035.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1970s1781100%2035
Capacity retiring by year
YearUnitsMW retiringShare of plant
20351781100%
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingNatural Gas Steam Turbine78119752035

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Gerald Andrus plant?

EIA lists no joint owners for Gerald Andrus. Entergy Mississippi LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Entergy Mississippi LLC charge homes?

Entergy Mississippi LLC, the operator of Gerald Andrus, had an average residential price of 13.87¢ per kWh and an average bill of $168 a month in 2025, 1% below the Mississippi average of 14.03¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Mississippi
Entergy Mississippi LLC13.87¢$1681% lower
Mississippi average14.03¢$166
U.S. average17.23¢$15123% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Gerald Andrus plant?

Gerald Andrus is in Greenville, Washington County, Mississippi, at 33.3500° N, 91.1167° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Mississippi are similar in size?

Mississippi has 28 operable natural gas plants with 12,678 MW of capacity, and Gerald Andrus' 781 MW is 6% of that.

Natural gas plants in Mississippi around this size
PlantCountyMW2025 MWh
Quantum Choctaw Power LLCChoctaw8514,264,190
RatcliffeKemper8403,984,740
CaledoniaLowndes8015,246,915
Gerald AndrusWashington781566,101
Hinds Energy FacilityHinds6001,926,168
R D MorrowLamar5582,805,424
AttalaAttala5512,221,476

Source: EIA Forms EIA-860 and EIA-923, 2025.