Wind power plant, New Hampshire
Granite Reliable Power wind power plant, New Hampshire
Granite Reliable Power is a 99 MW wind power plant in Coos County, New Hampshire, operated by NexteraEnergy, and it generated 193,139 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.0% of the generation reported in New Hampshire, and its capacity factor sits at the 15th percentile of U.S. wind plants. By 2025 generation it ranks 2,544th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Granite Reliable Power plant run compared with other wind plants?
The Granite Reliable Power plant had a capacity factor of 22% in 2025 on 99 MW of net summer capacity, the 15th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 81 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Granite Reliable Power | 22% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Granite Reliable Power plant generating more or less than last year?
Generation at Granite Reliable Power rose 2.1% from 2024 to 2025, from 189,118 MWh to 193,139 MWh. Through August 2026 it is running 8.5% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 189,118 |
| 2025 | 193,139 |
| 2026 through August | 136,142 |
| 2025, same months | 125,526 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 11,890 |
| July 2026 | 17,900 |
| June 2026 | 12,511 |
| May 2026 | 20,629 |
| April 2026 | 16,990 |
| March 2026 | 21,588 |
| February 2026 | 14,260 |
| January 2026 | 20,374 |
| December 2025 | 23,408 |
| November 2025 | 16,711 |
| October 2025 | 17,918 |
| September 2025 | 9,576 |
| August 2025 | 6,763 |
| July 2025 | 10,833 |
| June 2025 | 12,568 |
| May 2025 | 12,983 |
| April 2025 | 18,175 |
| March 2025 | 18,132 |
| February 2025 | 21,570 |
| January 2025 | 24,502 |
| December 2024 | 16,064 |
| November 2024 | 23,245 |
| October 2024 | 20,326 |
| September 2024 | 12,543 |
| August 2024 | 6,438 |
| July 2024 | 9,995 |
| June 2024 | 14,787 |
| May 2024 | 11,439 |
| April 2024 | 18,812 |
| March 2024 | 21,311 |
| February 2024 | 18,288 |
| January 2024 | 15,870 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Granite Reliable Power plant, and when do they retire?
1 operable generator totals 99 MW, with an average age of 13 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 99 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 99 | 2012 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Granite Reliable Power plant?
2 owners report shares in Granite Reliable Power; BAIF Granite Holdings LLC holds the largest named share, 89.5% or about 88.6 MW. NexteraEnergy operates the plant.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| BAIF Granite Holdings LLC | 89.5% | 89 | 172,821 |
| Freshet Wind Energy LLC | 10.5% | 10 | 20,318 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
Where is the Granite Reliable Power plant?
Granite Reliable Power is in Dummer, Coos County, New Hampshire, at 44.7044° N, 71.2925° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).
Source: EIA Form EIA-860, Plant, 2025 final.