Natural gas power plant, Virginia

Gravel Neck natural gas power plant, Virginia

Gravel Neck is a 408 MW power plant, 368 MW of it natural gas, in Surry County, Virginia, operated by Virginia Electric & Power Co, and it generated 119,980 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Virginia, and its capacity factor sits at the 17th percentile of U.S. natural gas plants. By 2025 generation it ranks 3,195th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

408 MWNameplate capacity
3%Capacity factor, 2025, natural gas units, 17th percentile, on 340 MW net summer
0.1%Of VA generation, 2025
38 yearsAverage generator age, by MW

How hard does the Gravel Neck plant run compared with other natural gas plants?

The Gravel Neck plant's natural gas units had a capacity factor of 3% in 2025 on 340 MW of net summer capacity, the 17th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 9 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Gravel Neck3%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its natural gas generators only. Values above 105% are left out of the comparison.

Is the Gravel Neck plant generating more or less than last year?

Gravel Neck generated 119,980 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 11 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024115,421
2025119,980
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202512,072
November 20258,459
October 20256,120
September 20257,931
August 202510,830
July 202513,212
June 202512,060
May 20257,351
April 20255,092
March 20258,307
February 20258,913
January 202519,632
December 20241,999
November 202419
October 202419,780
September 20244,938
August 20246,511
July 202440,380
June 20249,930
May 202422,064
April 20245,191
March 20241,104
February 20240
January 20243,506

Source: EIA Form EIA-923, through August 2026.

How much of Virginia's electricity comes from the Gravel Neck plant?

Gravel Neck made 0.1% of the 106,220,859 MWh reported by Virginia plants in 2025, from 1.3% of the state's 31,312 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 22nd largest of 259 plants in Virginia, the 842nd largest of 14,327 in the U.S. and the 541st largest of 1,962 natural gas plants on its natural gas units alone. By 2025 generation it is the 70th largest of 241 generating plants in the state.

Gravel Neck within Virginia, 2025
MeasureThis plantVirginiaShare
Capacity (MW)40831,3121.3%
Generation (MWh)119,980106,220,8590.1%
Natural gas capacity (MW)36815,1022.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Gravel Neck plant, and when do they retire?

6 operable generators total 408 MW, with an average age of 38 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1970s24010%none reported
1980s436890%none reported
Every generator, 6 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingPetroleum Liquids161970n/a
2OperatingPetroleum Liquids241970n/a
3OperatingNatural Gas Fired Combustion Turbine921989n/a
4OperatingNatural Gas Fired Combustion Turbine921989n/a
5OperatingNatural Gas Fired Combustion Turbine921989n/a
6OperatingNatural Gas Fired Combustion Turbine921989n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Gravel Neck plant?

EIA lists no joint owners for Gravel Neck. Virginia Electric & Power Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Virginia Electric & Power Co charge homes?

Virginia Electric & Power Co, the operator of Gravel Neck, had an average residential price of 15.20¢ per kWh and an average bill of $158 a month in 2025, 1% below the Virginia average of 15.28¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Virginia
Virginia Electric & Power Co15.20¢$1581% lower
Virginia average15.28¢$163
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

What fuels does the Gravel Neck plant use?

Gravel Neck has capacity on 2 fuels: 90% natural gas and 10% petroleum. In 2025, natural gas made 64% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Natural gas36890.2%76,510
Petroleum409.8%43,470

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Gravel Neck plant?

Gravel Neck is in Surry, Surry County, Virginia, at 37.1575° N, 76.6911° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Virginia are similar in size?

Virginia has 30 operable natural gas plants with 15,102 MW of capacity, and Gravel Neck's 368 MW is 2% of that.

Natural gas plants in Virginia around this size
PlantCountyMW2025 MWh
Hopewell CogenerationPrince George3991,754,029
Elizabeth River Power StationChesapeake City389107,983
DarbytownHenrico368123,359
Gravel NeckSurry36876,510
Gordonsville Energy LPLouisa3001,384,717
Wolf Hills EnergyWashington285286,951

Source: EIA Forms EIA-860 and EIA-923, 2025.