Gray County Wind Energy power plant, Kansas
Gray County Wind Energy is a 112 MW wind power plant in Gray County, Kansas, operated by Gray County Wind Energy LLC, and it generated 237,306 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Kansas, and its capacity factor sits at the 19th percentile of U.S. wind plants. By 2025 generation it ranks 2,286th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Gray County Wind Energy plant run compared with other wind plants?
The Gray County Wind Energy plant had a capacity factor of 24% in 2025 on 112 MW of net summer capacity, the 19th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 88 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Gray County Wind Energy | 24% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Gray County Wind Energy plant generating more or less than last year?
Generation at Gray County Wind Energy fell 10.1% from 2024 to 2025, from 264,095 MWh to 237,306 MWh.
| Period | MWh |
|---|---|
| 2024 | 264,095 |
| 2025 | 237,306 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 24,230 |
| November 2025 | 22,510 |
| October 2025 | 25,069 |
| September 2025 | 18,294 |
| August 2025 | 16,914 |
| July 2025 | 20,103 |
| June 2025 | 22,193 |
| May 2025 | 17,212 |
| April 2025 | 23,453 |
| March 2025 | 17,466 |
| February 2025 | 16,620 |
| January 2025 | 13,242 |
| December 2024 | 19,816 |
| November 2024 | 15,442 |
| October 2024 | 14,403 |
| September 2024 | 10,753 |
| August 2024 | 15,931 |
| July 2024 | 21,001 |
| June 2024 | 25,657 |
| May 2024 | 27,930 |
| April 2024 | 32,912 |
| March 2024 | 33,274 |
| February 2024 | 24,478 |
| January 2024 | 22,498 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Gray County Wind Energy plant, and when do they retire?
1 operable generator totals 112 MW, with an average age of 24 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 112 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| V47 | Operating | Onshore Wind Turbine | 112 | 2001 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Gray County Wind Energy plant?
EIA lists no joint owners for Gray County Wind Energy. Gray County Wind Energy LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Gray County Wind Energy plant?
Gray County Wind Energy is in Montezuma, Gray County, Kansas, at 37.6133° N, 100.3782° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Kansas are similar in size?
Kansas has 52 operable wind plants with 9,714 MW of capacity, and Gray County Wind Energy's 112 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Flat Ridge 4 | Harper | 134 | 282,655 |
| Cimarron Windpower II | Gray | 131 | 436,996 |
| Flat Ridge 3 | Kingman | 128 | 459,065 |
| Gray County Wind Energy | Gray | 112 | 237,306 |
| Spearville 3 LLC | Ford | 108 | 170,540 |
| Shooting Star | Kiowa | 104 | 164,544 |
| Smoky Hills Wind Project Phase I | Lincoln | 101 | 139,812 |
Source: EIA Forms EIA-860 and EIA-923, 2025.