Coal power plant, Colorado
Hayden coal power plant, Colorado
Hayden is a 465 MW coal power plant in Routt County, Colorado, operated by Public Service Co of Colorado, and it generated 2,274,874 MWh in 2025 (Forms EIA-860 and EIA-923). That is 4.1% of the generation reported in Colorado, and its capacity factor sits at the 66th percentile of U.S. coal plants. By 2025 generation it ranks 468th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Hayden plant run compared with other coal plants?
The Hayden plant had a capacity factor of 59% in 2025 on 441 MW of net summer capacity, the 66th percentile of the 181 U.S. coal plants with at least 20 MW. The typical coal plant reached 49%. That equals about 215 days at full output out of 365.
0%Shaded: the middle half of coal plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Hayden | 59% |
| Coal plants, 75th percentile | 63% |
| Coal plants, median | 49% |
| Coal plants, 25th percentile | 37% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Hayden plant generating more or less than last year?
Generation at Hayden rose 8.3% from 2024 to 2025, from 2,101,430 MWh to 2,274,874 MWh. Through August 2026 it is running 50.2% behind the same months of 2025.
2 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.
| Period | MWh |
|---|---|
| 2024 | 2,101,430 |
| 2025 | 2,274,874 |
| 2026 through August | 821,499 |
| 2025, same months | 1,650,483 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 188,178 |
| July 2026 | 179,073 |
| June 2026 | 159,201 |
| May 2026 | 152,683 |
| April 2026 | 89,573 |
| March 2026 | 61,363 |
| February 2026 | -4,286 |
| January 2026 | -4,286 |
| November 2025 | 208,914 |
| October 2025 | 212,783 |
| September 2025 | 202,694 |
| August 2025 | 220,873 |
| July 2025 | 238,838 |
| June 2025 | 237,436 |
| May 2025 | 178,504 |
| April 2025 | 200,433 |
| March 2025 | 230,956 |
| February 2025 | 165,121 |
| January 2025 | 178,322 |
| December 2024 | 166,535 |
| November 2024 | 183,292 |
| October 2024 | 171,932 |
| September 2024 | 182,275 |
| August 2024 | 217,251 |
| July 2024 | 199,350 |
| June 2024 | 181,061 |
| May 2024 | 141,303 |
| April 2024 | 105,500 |
| March 2024 | 183,658 |
| February 2024 | 115,448 |
| January 2024 | 253,825 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Hayden plant, and when do they retire?
2 operable generators total 465 MW, with an average age of 53 years weighted by capacity at the end of 2025. 465 MW, 100% of operable capacity, has a planned retirement, the first in 2027.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1960s | 1 | 190 | 41% | 2028 |
| 1970s | 1 | 275 | 59% | 2027 |
| Year | Units | MW retiring | Share of plant |
|---|---|---|---|
| 2027 | 1 | 275 | 59% |
| 2028 | 1 | 190 | 41% |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Steam Coal | 190 | 1965 | 2028 |
| 2 | Operating | Conventional Steam Coal | 275 | 1976 | 2027 |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Hayden plant?
3 owners report shares in Hayden; Public Service Co of Colorado holds the largest named share, 53.0% or about 246 MW. Public Service Co of Colorado operates the plant.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| Public Service Co of Colorado | 53.0% | 246 | 1,204,546 |
| Salt River Project | 29.6% | 138 | 673,135 |
| PacifiCorp | 17.5% | 81 | 397,193 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
What does Public Service Co of Colorado charge homes?
Public Service Co of Colorado, the operator of Hayden, had an average residential price of 15.90¢ per kWh and an average bill of $93 a month in 2025, 1% above the Colorado average of 15.69¢.
| Measure | Price | Monthly bill | Against Colorado |
|---|---|---|---|
| Public Service Co of Colorado | 15.90¢ | $93 | 1% higher |
| Colorado average | 15.69¢ | $103 | |
| U.S. average | 17.23¢ | $151 | 10% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Hayden plant?
Hayden is in Hayden, Routt County, Colorado, at 40.4856° N, 107.1850° W. It sits in the Public Service Company of Colorado balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which coal plants in Colorado are similar in size?
Colorado has 5 operable coal plants with 3,905 MW of capacity, and Hayden's 465 MW is 12% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Pawnee | Morgan | 552 | 1,168,494 |
| Hayden | Routt | 465 | 2,272,183 |
Source: EIA Forms EIA-860 and EIA-923, 2025.