Skip to main content
RateWatt

Solar power plant, North Carolina

Innovative Solar 67 power plant, North Carolina

Innovative Solar 67 is a 33.3 MW solar power plant in Pender County, North Carolina, operated by John Laing US Solar Corp., and it generated 61,850 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 34th percentile of U.S. solar plants. By 2025 generation it ranks 3,850th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

33.3 MWNameplate capacity
21%Capacity factor, 2025, 34th percentile, on 33.3 MW net summer
3,850thU.S. rank by generation, 2025
7 yearsAverage generator age, by MW

How hard does the Innovative Solar 67 plant run compared with other solar plants?

The Innovative Solar 67 plant had a capacity factor of 21% in 2025 on 33.3 MW of net summer capacity, the 34th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 77 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Innovative Solar 6721%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Innovative Solar 67 plant generating more or less than last year?

Generation at Innovative Solar 67 fell 7.9% from 2024 to 2025, from 67,120 MWh to 61,850 MWh. Through August 2026 it is running 0.1% ahead of the same months of 2025.

Net generation by period
PeriodMWh
202467,120
202561,850
2026 through August45,726
2025, same months45,702
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20265,751
July 20266,927
June 20267,277
May 20266,843
April 20266,565
March 20265,639
February 20263,428
January 20263,296
December 20252,852
November 20253,979
October 20254,339
September 20254,978
August 20255,230
July 20256,685
June 20256,990
May 20256,524
April 20257,035
March 20255,896
February 20253,792
January 20253,550
December 20243,313
November 20243,560
October 20245,514
September 20244,825
August 20246,328
July 20246,810
June 20248,043
May 20247,154
April 20246,886
March 20245,999
February 20244,677
January 20244,011

Source: EIA Form EIA-923, through August 2026.

How much of North Carolina's electricity comes from the Innovative Solar 67 plant?

Innovative Solar 67 made 0.0% of the 134,194,434 MWh reported by North Carolina plants in 2025, from 0.1% of the state's 39,933 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 101st largest of 928 plants in North Carolina, the 4,276th largest of 14,327 in the U.S. and the 998th largest of 7,223 solar plants. By 2025 generation it is the 95th largest of 872 generating plants in the state.

Innovative Solar 67 within North Carolina, 2025
MeasureThis plantNorth CarolinaShare
Capacity (MW)3339,9330.1%
Generation (MWh)61,850134,194,4340.0%
Solar capacity (MW)337,0250.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Innovative Solar 67 plant, and when do they retire?

1 operable generator totals 33.3 MW, with an average age of 7 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s133100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
IS067OperatingSolar Photovoltaic332018n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Innovative Solar 67 plant?

EIA lists no joint owners for Innovative Solar 67. John Laing US Solar Corp. operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Innovative Solar 67 plant?

Innovative Solar 67 is in Willard, Pender County, North Carolina, at 34.6233° N, 78.0054° W. It sits in the Duke Energy Progress East balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in North Carolina are similar in size?

North Carolina has 757 operable solar plants with 7,025 MW of capacity, and Innovative Solar 67's 33.3 MW is 0% of that.

Solar plants in North Carolina around this size
PlantCountyMW2025 MWh
Innovative Solar 31Bladen3553,573
Virginia Line Solar, LLCWarren3579,931
Innovative Solar 47Robeson3451,558
Innovative Solar 67Pender3361,850
Gaston Solar Power PlantGaston2544,291
East Nash PV2Nash2352,978
DD Fayetteville Solar NC LLCBladen2339,433

Source: EIA Forms EIA-860 and EIA-923, 2025.