Jasper natural gas power plant, South Carolina

Jasper is a 1,068 MW natural gas power plant in Jasper County, South Carolina, operated by Dominion Energy South Carolina, Inc, and it generated 3,603,980 MWh in 2025 (Forms EIA-860 and EIA-923). That is 3.5% of the generation reported in South Carolina, and its capacity factor sits at the 68th percentile of U.S. natural gas plants. By 2025 generation it ranks 326th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

1,068 MWNameplate capacity
46%Capacity factor, 2025, 68th percentile, on 895 MW net summer
3.5%Of SC generation, 2025
21 yearsAverage generator age, by MW

How hard does the Jasper plant run compared with other natural gas plants?

The Jasper plant had a capacity factor of 46% in 2025 on 895 MW of net summer capacity, the 68th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 168 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Jasper46%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Jasper plant generating more or less than last year?

Jasper generated 3,603,980 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 67.5% ahead of the same months of 2025. 2024 has output for only 11 months, so the two years are not compared.

Net generation by period
PeriodMWh
20244,613,681
20253,603,980
2026 through August3,052,174
2025, same months1,822,650
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026481,684
July 2026533,846
June 2026474,299
May 2026242,576
April 2026106,292
March 2026458,963
February 2026412,159
January 2026342,355
December 2025346,485
November 2025445,794
October 2025503,600
September 2025485,451
August 2025494,474
July 2025347,864
June 20250
May 20250
April 20250
March 2025186,433
February 2025365,434
January 2025428,445
December 2024378,166
November 2024148,331
October 2024567,069
September 2024472,068
August 2024519,965
July 2024508,693
June 2024458,496
May 2024479,607
April 2024326,207
March 20240
February 2024378,400
January 2024376,679

Source: EIA Form EIA-923, through August 2026.

How much of South Carolina's electricity comes from the Jasper plant?

Jasper made 3.5% of the 103,930,530 MWh reported by South Carolina plants in 2025, from 3.9% of the state's 27,220 MW of capacity. By capacity it is the 7th largest of 215 plants in South Carolina, the 284th largest of 14,327 in the U.S. and the 133rd largest of 1,962 natural gas plants. By 2025 generation it is the 9th largest of 197 generating plants in the state.

Jasper within South Carolina, 2025
MeasureThis plantSouth CarolinaShare
Capacity (MW)1,06827,2203.9%
Generation (MWh)3,603,980103,930,5303.5%
Natural gas capacity (MW)1,0687,95813.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Jasper plant, and when do they retire?

4 operable generators total 1,068 MW, with an average age of 21 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s41,068100%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CT1OperatingNatural Gas Fired Combined Cycle2132004n/a
CT2OperatingNatural Gas Fired Combined Cycle1992004n/a
CT3OperatingNatural Gas Fired Combined Cycle2132004n/a
ST1OperatingNatural Gas Fired Combined Cycle4442004n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Jasper plant?

EIA lists no joint owners for Jasper. Dominion Energy South Carolina, Inc operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Dominion Energy South Carolina, Inc charge homes?

Dominion Energy South Carolina, Inc, the operator of Jasper, had an average residential price of 16.41¢ per kWh and an average bill of $169 a month in 2025, 9% above the South Carolina average of 15.12¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst South Carolina
Dominion Energy South Carolina, Inc16.41¢$1699% higher
South Carolina average15.12¢$161
U.S. average17.23¢$15114% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Jasper plant?

Jasper is in Hardeeville, Jasper County, South Carolina, at 32.3594° N, 81.1242° W. It sits in the Dominion Energy South Carolina balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in South Carolina are similar in size?

South Carolina has 20 operable natural gas plants with 7,958 MW of capacity, and Jasper's 1,068 MW is 13% of that.

Natural gas plants in South Carolina around this size
PlantCountyMW2025 MWh
John S RaineyAnderson1,1544,796,999
JasperJasper1,0683,602,225
Broad River Energy CenterCherokee985994,724
W S LeeAnderson9555,983,958
Mill Creek (SC)Cherokee799115,743

Source: EIA Forms EIA-860 and EIA-923, 2025.