Johnston LFG Turbine Plant, Rhode Island

Johnston LFG Turbine Plant is a 35.7 MW biomass power plant in Providence County, Rhode Island, operated by Rhode Island LFG Genco, and it generated 181,500 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.9% of the generation reported in Rhode Island, and its capacity factor sits at the 78th percentile of U.S. biomass plants. By 2025 generation it ranks 2,628th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

35.7 MWNameplate capacity
67%Capacity factor, 2025, 78th percentile, on 30.9 MW net summer
1.9%Of RI generation, 2025
12 yearsAverage generator age, by MW

How hard does Johnston LFG Turbine Plant run compared with other biomass plants?

Johnston LFG Turbine Plant had a capacity factor of 67% in 2025 on 30.9 MW of net summer capacity, the 78th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 245 days at full output out of 365.

0%Shaded: the middle half of biomass plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Johnston LFG Turbine Plant67%
Biomass plants, 75th percentile65%
Biomass plants, median48%
Biomass plants, 25th percentile35%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is Johnston LFG Turbine Plant generating more or less than last year?

Johnston LFG Turbine Plant generated 181,500 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 4.3% ahead of the same months of 2025. 2024 has output for only 11 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024195,099
2025181,500
2026 through August127,898
2025, same months122,604
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202617,278
July 202616,881
June 202616,256
May 202616,506
April 202612,597
March 202613,614
February 202617,108
January 202617,658
December 202517,824
November 202518,184
October 202516,944
September 20255,944
August 20250
July 202518,641
June 202518,084
May 202516,570
April 202515,221
March 202519,224
February 202516,991
January 202517,873
December 20247,097
November 20240
October 202412,863
September 202418,677
August 202418,255
July 202420,473
June 202419,966
May 202421,329
April 202414,568
March 202420,754
February 202419,849
January 202421,266

Source: EIA Form EIA-923, through August 2026.

How much of Rhode Island's electricity comes from Johnston LFG Turbine Plant?

Johnston LFG Turbine Plant made 1.9% of the 9,791,976 MWh reported by Rhode Island plants in 2025, from 1.4% of the state's 2,577 MW of capacity. Its share of output is 1.3 times its share of capacity. By capacity it is the 8th largest of 112 plants in Rhode Island, the 4,225th largest of 14,327 in the U.S. and the 129th largest of 585 biomass plants. By 2025 generation it is the 6th largest of 106 generating plants in the state.

Johnston LFG Turbine Plant within Rhode Island, 2025
MeasureThis plantRhode IslandShare
Capacity (MW)362,5771.4%
Generation (MWh)181,5009,791,9761.9%
Biomass capacity (MW)364578.8%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at Johnston LFG Turbine Plant, and when do they retire?

5 operable generators total 35.7 MW, with an average age of 12 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s536100%none reported
Every generator, 5 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GENS1OperatingLandfill Gas112013n/a
GENT1OperatingLandfill Gas62013n/a
GENT2OperatingLandfill Gas62013n/a
GENT3OperatingLandfill Gas62013n/a
GENT4OperatingLandfill Gas62013n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns Johnston LFG Turbine Plant?

EIA lists no joint owners for Johnston LFG Turbine Plant. Rhode Island LFG Genco operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is Johnston LFG Turbine Plant?

Johnston LFG Turbine Plant is in Johnston, Providence County, Rhode Island, at 41.8033° N, 71.5233° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).

Source: EIA Form EIA-860, Plant, 2025 final.