Biomass power plant, Rhode Island
Johnston LFG Turbine Plant, Rhode Island
Johnston LFG Turbine Plant is a 35.7 MW biomass power plant in Providence County, Rhode Island, operated by Rhode Island LFG Genco, and it generated 181,500 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.9% of the generation reported in Rhode Island, and its capacity factor sits at the 78th percentile of U.S. biomass plants. By 2025 generation it ranks 2,628th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does Johnston LFG Turbine Plant run compared with other biomass plants?
Johnston LFG Turbine Plant had a capacity factor of 67% in 2025 on 30.9 MW of net summer capacity, the 78th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 245 days at full output out of 365.
0%Shaded: the middle half of biomass plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Johnston LFG Turbine Plant | 67% |
| Biomass plants, 75th percentile | 65% |
| Biomass plants, median | 48% |
| Biomass plants, 25th percentile | 35% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is Johnston LFG Turbine Plant generating more or less than last year?
Johnston LFG Turbine Plant generated 181,500 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 4.3% ahead of the same months of 2025. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 195,099 |
| 2025 | 181,500 |
| 2026 through August | 127,898 |
| 2025, same months | 122,604 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 17,278 |
| July 2026 | 16,881 |
| June 2026 | 16,256 |
| May 2026 | 16,506 |
| April 2026 | 12,597 |
| March 2026 | 13,614 |
| February 2026 | 17,108 |
| January 2026 | 17,658 |
| December 2025 | 17,824 |
| November 2025 | 18,184 |
| October 2025 | 16,944 |
| September 2025 | 5,944 |
| August 2025 | 0 |
| July 2025 | 18,641 |
| June 2025 | 18,084 |
| May 2025 | 16,570 |
| April 2025 | 15,221 |
| March 2025 | 19,224 |
| February 2025 | 16,991 |
| January 2025 | 17,873 |
| December 2024 | 7,097 |
| November 2024 | 0 |
| October 2024 | 12,863 |
| September 2024 | 18,677 |
| August 2024 | 18,255 |
| July 2024 | 20,473 |
| June 2024 | 19,966 |
| May 2024 | 21,329 |
| April 2024 | 14,568 |
| March 2024 | 20,754 |
| February 2024 | 19,849 |
| January 2024 | 21,266 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at Johnston LFG Turbine Plant, and when do they retire?
5 operable generators total 35.7 MW, with an average age of 12 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 5 | 36 | 100% | none reported |
Every generator, 5 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GENS1 | Operating | Landfill Gas | 11 | 2013 | n/a |
| GENT1 | Operating | Landfill Gas | 6 | 2013 | n/a |
| GENT2 | Operating | Landfill Gas | 6 | 2013 | n/a |
| GENT3 | Operating | Landfill Gas | 6 | 2013 | n/a |
| GENT4 | Operating | Landfill Gas | 6 | 2013 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns Johnston LFG Turbine Plant?
EIA lists no joint owners for Johnston LFG Turbine Plant. Rhode Island LFG Genco operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is Johnston LFG Turbine Plant?
Johnston LFG Turbine Plant is in Johnston, Providence County, Rhode Island, at 41.8033° N, 71.5233° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).
Source: EIA Form EIA-860, Plant, 2025 final.