Natural gas power plant, Arkansas
Jonesboro City Water & Light Plant, Arkansas
Jonesboro City Water & Light Plant is a 224 MW natural gas power plant in Craighead County, Arkansas, operated by City Water and Light Plant-(AR), and it generated 56,623 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Arkansas, and its capacity factor sits at the 20th percentile of U.S. natural gas plants. By 2025 generation it ranks 3,934th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does Jonesboro City Water & Light Plant run compared with other natural gas plants?
Jonesboro City Water & Light Plant had a capacity factor of 4% in 2025 on 177 MW of net summer capacity, the 20th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 13 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Jonesboro City Water & Light Plant | 4% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is Jonesboro City Water & Light Plant generating more or less than last year?
Generation at Jonesboro City Water & Light Plant fell 27.4% from 2024 to 2025, from 78,039 MWh to 56,623 MWh.
| Period | MWh |
|---|---|
| 2024 | 78,039 |
| 2025 | 56,623 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 3,819 |
| November 2025 | 5,065 |
| October 2025 | 4,874 |
| September 2025 | 5,893 |
| August 2025 | 6,721 |
| July 2025 | 6,699 |
| June 2025 | 5,896 |
| May 2025 | 2,647 |
| April 2025 | 3,366 |
| March 2025 | 3,765 |
| February 2025 | 3,422 |
| January 2025 | 4,456 |
| December 2024 | 619 |
| November 2024 | 5,085 |
| October 2024 | 5,629 |
| September 2024 | 6,781 |
| August 2024 | 9,695 |
| July 2024 | 8,389 |
| June 2024 | 3,709 |
| May 2024 | 13,859 |
| April 2024 | 19,437 |
| March 2024 | 648 |
| February 2024 | 327 |
| January 2024 | 3,861 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at Jonesboro City Water & Light Plant, and when do they retire?
5 operable generators total 224 MW, with an average age of 23 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1990s | 2 | 46 | 20% | none reported |
| 2000s | 3 | 178 | 80% | none reported |
Every generator, 5 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| SN01 | Operating | Natural Gas Fired Combustion Turbine | 25 | 1999 | n/a |
| SN02 | Operating | Natural Gas Fired Combustion Turbine | 21 | 1999 | n/a |
| SN04 | Operating | Natural Gas Fired Combustion Turbine | 61 | 2000 | n/a |
| SN06 | Operating | Natural Gas Fired Combustion Turbine | 57 | 2003 | n/a |
| SN07 | Operating | Natural Gas Fired Combustion Turbine | 61 | 2007 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns Jonesboro City Water & Light Plant?
EIA lists no joint owners for Jonesboro City Water & Light Plant. City Water and Light Plant-(AR) operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does City Water and Light Plant charge homes?
City Water and Light Plant, the operator of Jonesboro City Water & Light Plant, had an average residential price of 7.13¢ per kWh and an average bill of $90 a month in 2025, 45% below the Arkansas average of 12.87¢.
| Measure | Price | Monthly bill | Against Arkansas |
|---|---|---|---|
| City Water and Light Plant | 7.13¢ | $90 | 45% lower |
| Arkansas average | 12.87¢ | $138 | |
| U.S. average | 17.23¢ | $151 | 34% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is Jonesboro City Water & Light Plant?
Jonesboro City Water & Light Plant is in Jonesboro, Craighead County, Arkansas, at 35.8486° N, 90.7254° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Arkansas are similar in size?
Arkansas has 18 operable natural gas plants with 7,130 MW of capacity, and Jonesboro City Water & Light Plant's 224 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Harry D Mattison Gas Plant | Washington | 349 | 220,482 |
| Pine Bluff Energy Center | Jefferson | 230 | 1,113,270 |
| Jonesboro City Water & Light Plant | Craighead | 224 | 56,587 |
| Thomas Fitzhugh | Franklin | 185 | 472,109 |
| Fulton (AR) | Hempstead | 155 | 285,318 |
| McClellan (AR) | Ouachita | 136 | 19,833 |
Source: EIA Forms EIA-860 and EIA-923, 2025.