Hydro power plant, California
Kern River 3 hydroelectric power plant, California
Kern River 3 is a 40.3 MW hydro power plant in Kern County, California, operated by Southern California Edison Co, and it generated 142,601 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 67th percentile of U.S. hydro plants. By 2025 generation it ranks 2,983rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Kern River 3 plant run compared with other hydro plants?
The Kern River 3 plant had a capacity factor of 40% in 2025 on 40.2 MW of net summer capacity, the 67th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 148 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Kern River 3 | 40% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Kern River 3 plant generating more or less than last year?
Generation at Kern River 3 fell 0.1% from 2024 to 2025, from 142,766 MWh to 142,601 MWh.
| Period | MWh |
|---|---|
| 2024 | 142,766 |
| 2025 | 142,601 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 10,268 |
| November 2025 | 7,154 |
| October 2025 | 5,712 |
| September 2025 | 2,776 |
| August 2025 | 2,725 |
| July 2025 | 4,351 |
| June 2025 | 20,761 |
| May 2025 | 18,669 |
| April 2025 | 21,993 |
| March 2025 | 22,827 |
| February 2025 | 17,253 |
| January 2025 | 8,112 |
| December 2024 | 10,196 |
| November 2024 | 7,651 |
| October 2024 | 3,720 |
| September 2024 | 4,136 |
| August 2024 | 6,638 |
| July 2024 | 17,014 |
| June 2024 | 20,947 |
| May 2024 | 18,034 |
| April 2024 | 20,249 |
| March 2024 | 9,389 |
| February 2024 | 12,445 |
| January 2024 | 12,347 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Kern River 3 plant, and when do they retire?
2 operable generators total 40.3 MW, with an average age of 104 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1920s | 2 | 40 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 21 | 1921 | n/a |
| 2 | Operating | Conventional Hydroelectric | 20 | 1921 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Kern River 3 plant?
EIA lists no joint owners for Kern River 3. Southern California Edison Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Southern California Edison Co charge homes?
Southern California Edison Co, the operator of Kern River 3, had an average residential price of 31.48¢ per kWh and an average bill of $149 a month in 2025, about the same as the California average of 31.35¢.
| Measure | Price | Monthly bill | Against California |
|---|---|---|---|
| Southern California Edison Co | 31.48¢ | $149 | about the same |
| California average | 31.35¢ | $155 | |
| U.S. average | 17.23¢ | $151 | 45% lower |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Kern River 3 plant?
Kern River 3 is in Kernville, Kern County, California, at 35.7762° N, 118.4362° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in California are similar in size?
California has 238 operable hydro plants with 9,936 MW of capacity, and Kern River 3's 40.3 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Chicago Park | Nevada | 44 | 65,178 |
| Salt Springs | Amador | 42 | 113,368 |
| Forbestown | Butte | 42 | 114,901 |
| Kern River 3 | Kern | 40 | 142,601 |
| Butt Valley | Plumas | 40 | 145,340 |
| Union Valley | El Dorado | 39 | 89,140 |
| Control Gorge | Inyo | 38 | 46,367 |
Source: EIA Forms EIA-860 and EIA-923, 2025.