Skip to main content
RateWatt

Wind power plant, Texas

King Creek Wind Farm 2, LLC power plant, Texas

King Creek Wind Farm 2, LLC is a 209 MW wind power plant in Throckmorton County, Texas, operated by King Creek Wind Farm 2, LLC, and it generated 645,992 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 58th percentile of U.S. wind plants. By 2025 generation it ranks 1,064th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

209 MWNameplate capacity
35%Capacity factor, 2025, 58th percentile, on 209 MW net summer
0.1%Of TX generation, 2025
3 yearsAverage generator age, by MW

How hard does the King Creek Wind Farm 2, LLC plant run compared with other wind plants?

The King Creek Wind Farm 2, LLC plant had a capacity factor of 35% in 2025 on 209 MW of net summer capacity, the 58th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 129 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
King Creek Wind Farm 2, LLC35%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the King Creek Wind Farm 2, LLC plant generating more or less than last year?

Generation at King Creek Wind Farm 2, LLC rose 5.6% from 2024 to 2025, from 611,861 MWh to 645,992 MWh. Through August 2026 it is running 14.4% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024611,861
2025645,992
2026 through August489,240
2025, same months427,684
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202651,947
July 202648,972
June 202669,060
May 202656,771
April 202670,832
March 202679,966
February 202653,038
January 202658,654
December 202565,709
November 202555,136
October 202556,660
September 202540,803
August 202540,254
July 202547,797
June 202560,720
May 202549,165
April 202565,231
March 202564,637
February 202545,875
January 202554,005
December 202448,247
November 202457,624
October 202439,550
September 202430,670
August 202445,411
July 202443,535
June 202453,059
May 202456,209
April 202464,344
March 202462,764
February 202462,517
January 202447,931

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the King Creek Wind Farm 2, LLC plant?

King Creek Wind Farm 2, LLC made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. By capacity it is the 271st largest of 1,023 plants in Texas, the 1,442nd largest of 14,327 in the U.S. and the 215th largest of 1,358 wind plants. By 2025 generation it is the 207th largest of 816 generating plants in the state.

King Creek Wind Farm 2, LLC within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)209195,9660.1%
Generation (MWh)645,992592,896,1760.1%
Wind capacity (MW)20943,9420.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the King Creek Wind Farm 2, LLC plant, and when do they retire?

1 operable generator totals 209 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1209100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
KC2OperatingOnshore Wind Turbine2092022n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the King Creek Wind Farm 2, LLC plant?

EIA lists no joint owners for King Creek Wind Farm 2, LLC. King Creek Wind Farm 2, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the King Creek Wind Farm 2, LLC plant?

King Creek Wind Farm 2, LLC is in Throckmorton, Throckmorton County, Texas, at 33.1824° N, 99.3899° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Texas are similar in size?

Texas has 228 operable wind plants with 43,942 MW of capacity, and King Creek Wind Farm 2, LLC's 209 MW is 0% of that.

Wind plants in Texas around this size
PlantCountyMW2025 MWh
Canadian Breaks, LLCDeaf Smith210756,298
Reloj del Sol Wind FarmZapata209592,321
Roscoe Wind Farm LLCNolan209364,344
King Creek Wind Farm 2, LLCThrockmorton209645,992
Rattlesnake DenGlasscock207689,334
1370 ShannonClay204444,456
Magic Valley Wind Farm I LLCWillacy203482,905

Source: EIA Forms EIA-860 and EIA-923, 2025.