Laurel Mountain Hybrid wind power plant, West Virginia

Laurel Mountain Hybrid is a 97.6 MW wind power plant in Barbour County, West Virginia, operated by AES Distributed Energy, and it generated 265,532 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in West Virginia, and its capacity factor sits at the 45th percentile of U.S. wind plants. By 2025 generation it ranks 2,134th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

97.6 MWNameplate capacity
31%Capacity factor, 2025, 45th percentile, on 97.6 MW net summer
0.5%Of WV generation, 2025
14 yearsAverage generator age, by MW

How hard does the Laurel Mountain Hybrid plant run compared with other wind plants?

The Laurel Mountain Hybrid plant had a capacity factor of 31% in 2025 on 97.6 MW of net summer capacity, the 45th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 114 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Laurel Mountain Hybrid31%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Laurel Mountain Hybrid plant generating more or less than last year?

Generation at Laurel Mountain Hybrid rose 10.2% from 2024 to 2025, from 241,013 MWh to 265,532 MWh. Through August 2026 it is running 2.1% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024241,013
2025265,532
2026 through August174,005
2025, same months170,405
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202610,036
July 20267,173
June 202617,740
May 202622,054
April 202629,561
March 202633,765
February 202620,515
January 202633,161
December 202527,341
November 202538,322
October 202521,981
September 20257,483
August 20256,241
July 20256,298
June 20259,507
May 202528,123
April 202526,257
March 202534,809
February 202530,904
January 202528,266
December 202430,310
November 202426,412
October 202412,760
September 202415,591
August 20245,895
July 20249,314
June 202417,561
May 202415,045
April 202428,827
March 202434,812
February 202421,655
January 202422,831

Source: EIA Form EIA-923, through August 2026.

How much of West Virginia's electricity comes from the Laurel Mountain Hybrid plant?

Laurel Mountain Hybrid made 0.5% of the 53,389,456 MWh reported by West Virginia plants in 2025, from 0.6% of the state's 16,061 MW of capacity. By capacity it is the 19th largest of 42 plants in West Virginia, the 2,779th largest of 14,327 in the U.S. and the 712th largest of 1,358 wind plants. By 2025 generation it is the 19th largest of 40 generating plants in the state.

Laurel Mountain Hybrid within West Virginia, 2025
MeasureThis plantWest VirginiaShare
Capacity (MW)9816,0610.6%
Generation (MWh)265,53253,389,4560.5%
Wind capacity (MW)9885611.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Laurel Mountain Hybrid plant, and when do they retire?

1 operable generator totals 97.6 MW, with an average age of 14 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 1 has already retired, totalling 16 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s198100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingOnshore Wind Turbine982011n/a
2RetiredBatteries1620112025

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Laurel Mountain Hybrid plant?

EIA lists no joint owners for Laurel Mountain Hybrid. AES Distributed Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Laurel Mountain Hybrid plant?

Laurel Mountain Hybrid is in Belington, Barbour County, West Virginia, at 39.0072° N, 79.8866° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in West Virginia are similar in size?

West Virginia has 8 operable wind plants with 856 MW of capacity, and Laurel Mountain Hybrid's 97.6 MW is 11% of that.

Wind plants in West Virginia around this size
PlantCountyMW2025 MWh
Black Rock WindMineral115396,403
New Creek WindGrant103292,693
Beech Ridge Energy LLCGreenbrier101269,429
Laurel Mountain HybridBarbour98267,350
Mountaineer Wind Energy CenterTucker66113,497
Beech Ridge II Wind Energy CenterGreenbrier56127,268
Pinnacle Wind Force LLCMineral54192,942

Source: EIA Forms EIA-860 and EIA-923, 2025.