Leesville hydroelectric power plant, Virginia

Leesville is a 40 MW hydro power plant in Pittsylvania County, Virginia, operated by Appalachian Power Co, and it generated 45,735 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 7th percentile of U.S. hydro plants. By 2025 generation it ranks 4,204th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

40 MWNameplate capacity
10%Capacity factor, 2025, 7th percentile, on 50 MW net summer
4,204thU.S. rank by generation, 2025
61 yearsAverage generator age, by MW

How hard does the Leesville plant run compared with other hydro plants?

The Leesville plant had a capacity factor of 10% in 2025 on 50 MW of net summer capacity, the 7th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 38 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Leesville10%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Leesville plant generating more or less than last year?

Generation at Leesville fell 5.4% from 2024 to 2025, from 48,365 MWh to 45,735 MWh.

Net generation by period
PeriodMWh
202448,365
202545,735
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20251,779
November 20251,645
October 20251,459
September 20252,668
August 20252,876
July 20253,411
June 20253,724
May 20256,289
April 20253,858
March 20253,731
February 202511,473
January 20252,822
December 20242,231
November 20241,155
October 20243,907
September 20245,527
August 20242,245
July 20242,308
June 20242,203
May 20243,108
April 20245,165
March 20246,131
February 20245,033
January 20249,352

Source: EIA Form EIA-923, through August 2026.

How much of Virginia's electricity comes from the Leesville plant?

Leesville made 0.0% of the 106,220,859 MWh reported by Virginia plants in 2025, from 0.1% of the state's 31,312 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 85th largest of 259 plants in Virginia, the 4,074th largest of 14,327 in the U.S. and the 310th largest of 1,393 hydro plants. By 2025 generation it is the 87th largest of 241 generating plants in the state.

Leesville within Virginia, 2025
MeasureThis plantVirginiaShare
Capacity (MW)4031,3120.1%
Generation (MWh)45,735106,220,8590.0%
Hydro capacity (MW)408224.9%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Leesville plant, and when do they retire?

2 operable generators total 40 MW, with an average age of 61 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1960s240100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric201964n/a
2OperatingConventional Hydroelectric201964n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Leesville plant?

EIA lists no joint owners for Leesville. Appalachian Power Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Appalachian Power Co charge homes?

Appalachian Power Co, the operator of Leesville, had an average residential price of 17.16¢ per kWh and an average bill of $186 a month in 2025, 12% above the Virginia average of 15.28¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Virginia
Appalachian Power Co17.16¢$18612% higher
Virginia average15.28¢$163
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Leesville plant?

Leesville is in Hurt, Pittsylvania County, Virginia, at 37.0933° N, 79.4025° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Virginia are similar in size?

Virginia has 23 operable hydro plants with 822 MW of capacity, and Leesville's 40 MW is 5% of that.

Hydro plants in Virginia around this size
PlantCountyMW2025 MWh
ClaytorPulaski75194,008
LeesvillePittsylvania4045,735
Byllesby 2Carroll222,126

Source: EIA Forms EIA-860 and EIA-923, 2025.