Motiva Enterprises Port Arthur Refinery is a 277 MW power plant, 226 MW of it natural gas, in Jefferson County, Texas, operated by Motiva Enterprises LLC, and it generated 1,609,437 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Texas, and its capacity factor sits at the 96th percentile of U.S. natural gas plants. By 2025 generation it ranks 573rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Motiva Enterprises Port Arthur Refinery plant run compared with other natural gas plants?
The Motiva Enterprises Port Arthur Refinery plant's natural gas units had a capacity factor of 84% in 2025 on 199 MW of net summer capacity, the 96th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 307 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Motiva Enterprises Port Arthur Refinery | 84% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its natural gas generators only. Values above 105% are left out of the comparison.
Is the Motiva Enterprises Port Arthur Refinery plant generating more or less than last year?
Generation at Motiva Enterprises Port Arthur Refinery fell 3.0% from 2024 to 2025, from 1,659,896 MWh to 1,609,437 MWh. Through August 2026 it is running 10.0% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 1,659,896 |
| 2025 | 1,609,437 |
| 2026 through August | 1,152,557 |
| 2025, same months | 1,047,754 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 148,248 |
| July 2026 | 147,544 |
| June 2026 | 142,678 |
| May 2026 | 138,828 |
| April 2026 | 148,382 |
| March 2026 | 156,255 |
| February 2026 | 133,968 |
| January 2026 | 136,653 |
| December 2025 | 147,744 |
| November 2025 | 140,873 |
| October 2025 | 144,066 |
| September 2025 | 128,999 |
| August 2025 | 114,768 |
| July 2025 | 119,169 |
| June 2025 | 127,254 |
| May 2025 | 132,131 |
| April 2025 | 134,843 |
| March 2025 | 141,621 |
| February 2025 | 131,553 |
| January 2025 | 146,415 |
| December 2024 | 133,374 |
| November 2024 | 139,051 |
| October 2024 | 146,570 |
| September 2024 | 133,765 |
| August 2024 | 122,131 |
| July 2024 | 131,488 |
| June 2024 | 126,900 |
| May 2024 | 143,648 |
| April 2024 | 130,749 |
| March 2024 | 146,074 |
| February 2024 | 145,510 |
| January 2024 | 160,636 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Motiva Enterprises Port Arthur Refinery plant, and when do they retire?
9 operable generators total 277 MW, with an average age of 29 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 2 have already retired, totalling 40.1 MW.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1950s | 1 | 16 | 6% | none reported |
| 1960s | 1 | 10 | 4% | none reported |
| 1970s | 2 | 44 | 16% | none reported |
| 1980s | 1 | 41 | 15% | none reported |
| 2010s | 4 | 166 | 60% | none reported |
Every generator, 11 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GN32 | Operating | Other Gases | 16 | 1957 | n/a |
| GN31 | Operating | Other Gases | 10 | 1962 | n/a |
| GN34 | Operating | Natural Gas Fired Combustion Turbine | 19 | 1970 | n/a |
| GN33 | Operating | Other Gases | 26 | 1978 | n/a |
| GN35 | Operating | Natural Gas Fired Combined Cycle | 41 | 1983 | n/a |
| GN41 | Operating | Natural Gas Fired Combined Cycle | 42 | 2011 | n/a |
| GN42 | Operating | Natural Gas Fired Combined Cycle | 42 | 2011 | n/a |
| GN43 | Operating | Natural Gas Fired Combined Cycle | 42 | 2011 | n/a |
| GN44 | Operating | Natural Gas Fired Combined Cycle | 42 | 2011 | n/a |
| GN26 | Retired | Natural Gas Fired Combined Cycle | 19 | 1970 | 2012 |
| GN27 | Retired | Natural Gas Fired Combined Cycle | 21 | 1984 | 2011 |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Motiva Enterprises Port Arthur Refinery plant?
EIA lists no joint owners for Motiva Enterprises Port Arthur Refinery. Motiva Enterprises LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What fuels does the Motiva Enterprises Port Arthur Refinery plant use?
Motiva Enterprises Port Arthur Refinery has capacity on 2 fuels: 82% natural gas and 18% other-fuel. In 2025, natural gas made 91% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Natural gas | 226 | 81.5% | 1,467,230 |
| Other-fuel | 51 | 18.5% | 142,207 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Motiva Enterprises Port Arthur Refinery plant?
Motiva Enterprises Port Arthur Refinery is in Port Arthur, Jefferson County, Texas, at 29.8885° N, 93.9510° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Texas are similar in size?
Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Motiva Enterprises Port Arthur Refinery's 226 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Trinidad (TX) | Henderson | 239 | 431,940 |
| Exelon LaPorte Generating Station | Harris | 236 | 70,669 |
| Leon Creek | Bexar | 230 | 385,732 |
| Motiva Enterprises Port Arthur Refinery | Jefferson | 226 | 1,467,230 |
| Denton Energy Center | Denton | 226 | 288,706 |
| Red Gate Power Plant | Hidalgo | 224 | 365,952 |
| Decker Creek | Travis | 206 | 0 |
Source: EIA Forms EIA-860 and EIA-923, 2025.