Wind power plant, Oklahoma
NextEra-Blackwell Wind, LLC power plant, Oklahoma
NextEra-Blackwell Wind, LLC is a 59.8 MW wind power plant in Kay County, Oklahoma, operated by Blackwell Wind, LLC, and it generated 83,310 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Oklahoma, and its capacity factor sits at the 5th percentile of U.S. wind plants. By 2025 generation it ranks 3,603rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the NextEra-Blackwell Wind, LLC plant run compared with other wind plants?
The NextEra-Blackwell Wind, LLC plant had a capacity factor of 16% in 2025 on 59.8 MW of net summer capacity, the 5th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 58 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| NextEra-Blackwell Wind, LLC | 16% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the NextEra-Blackwell Wind, LLC plant generating more or less than last year?
Generation at NextEra-Blackwell Wind, LLC fell 3.9% from 2024 to 2025, from 86,729 MWh to 83,310 MWh.
| Period | MWh |
|---|---|
| 2024 | 86,729 |
| 2025 | 83,310 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 10,250 |
| November 2025 | 5,176 |
| October 2025 | 5,818 |
| September 2025 | 6,672 |
| August 2025 | 7,910 |
| July 2025 | 11,027 |
| June 2025 | 6,055 |
| May 2025 | 7,491 |
| April 2025 | 4,456 |
| March 2025 | 4,624 |
| February 2025 | 6,987 |
| January 2025 | 6,844 |
| December 2024 | 10,283 |
| November 2024 | 5,365 |
| October 2024 | 5,536 |
| September 2024 | 6,775 |
| August 2024 | 10,080 |
| July 2024 | 5,748 |
| June 2024 | 7,424 |
| May 2024 | 7,724 |
| April 2024 | 6,990 |
| March 2024 | 7,008 |
| February 2024 | 8,192 |
| January 2024 | 5,604 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the NextEra-Blackwell Wind, LLC plant, and when do they retire?
1 operable generator totals 59.8 MW, with an average age of 13 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 60 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| WT | Operating | Onshore Wind Turbine | 60 | 2012 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the NextEra-Blackwell Wind, LLC plant?
EIA lists no joint owners for NextEra-Blackwell Wind, LLC. Blackwell Wind, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the NextEra-Blackwell Wind, LLC plant?
NextEra-Blackwell Wind, LLC is in Blackwell, Kay County, Oklahoma, at 36.8467° N, 97.4175° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Oklahoma are similar in size?
Oklahoma has 69 operable wind plants with 13,344 MW of capacity, and NextEra-Blackwell Wind, LLC's 59.8 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Sleeping Bear LLC | Harper | 95 | 84,460 |
| Blue Canyon Windpower | Comanche | 74 | 0 |
| Little Elk Wind Project LLC | Washita | 74 | 318,592 |
| NextEra-Blackwell Wind, LLC | Kay | 60 | 83,310 |
Source: EIA Forms EIA-860 and EIA-923, 2025.