Natural gas power plant, Washington
Northeast natural gas power plant, Washington
Northeast (WA) is a 61.8 MW natural gas power plant in Spokane County, Washington, operated by Avista Corp, and it generated 526 MWh in 2025 (Forms EIA-860 and EIA-923). By 2025 generation it ranks 12,104th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Northeast (WA) plant run compared with other natural gas plants?
The Northeast (WA) plant had a capacity factor of under 1% in 2025 on 45 MW of net summer capacity, below nearly all of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. It ran for only a few hours of the year at full output.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Northeast (WA) | under 1% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Northeast (WA) plant generating more or less than last year?
Generation at Northeast (WA) fell 55.8% from 2024 to 2025, from 1,189 MWh to 526 MWh.
| Period | MWh |
|---|---|
| 2024 | 1,189 |
| 2025 | 526 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 36 |
| November 2025 | 31 |
| October 2025 | 45 |
| September 2025 | 58 |
| August 2025 | 54 |
| July 2025 | 60 |
| June 2025 | 41 |
| May 2025 | 19 |
| April 2025 | 28 |
| March 2025 | 43 |
| February 2025 | 53 |
| January 2025 | 58 |
| December 2024 | 105 |
| November 2024 | 100 |
| October 2024 | 98 |
| September 2024 | 110 |
| August 2024 | 117 |
| July 2024 | 123 |
| June 2024 | 58 |
| May 2024 | 27 |
| April 2024 | 93 |
| March 2024 | 109 |
| February 2024 | 122 |
| January 2024 | 126 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Northeast (WA) plant, and when do they retire?
1 operable generator totals 61.8 MW, with an average age of 47 years weighted by capacity at the end of 2025. 61.8 MW, 100% of operable capacity, has a planned retirement, the first in 2035.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 1 | 62 | 100% | 2035 |
| Year | Units | MW retiring | Share of plant |
|---|---|---|---|
| 2035 | 1 | 62 | 100% |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Natural Gas Fired Combustion Turbine | 62 | 1978 | 2035 |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Northeast (WA) plant?
EIA lists no joint owners for Northeast (WA). Avista Corp operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Avista Corp charge homes?
Avista Corp, the operator of Northeast (WA), had an average residential price of 14.16¢ per kWh and an average bill of $130 a month in 2025, 7% above the Washington average of 13.17¢.
| Measure | Price | Monthly bill | Against Washington |
|---|---|---|---|
| Avista Corp | 14.16¢ | $130 | 7% higher |
| Washington average | 13.17¢ | $124 | |
| U.S. average | 17.23¢ | $151 | 31% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Northeast (WA) plant?
Northeast (WA) is in Spokane, Spokane County, Washington, at 47.7351° N, 117.3705° W. It sits in the Avista Corporation balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.