Geothermal power plant, California
Ormesa III geothermal power plant, California
Ormesa III is a 45.6 MW geothermal power plant in Imperial County, California, operated by Ormat Nevada Inc, and it generated 77,316 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 6th percentile of U.S. geothermal plants. By 2025 generation it ranks 3,681st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Ormesa III plant run compared with other geothermal plants?
The Ormesa III plant had a capacity factor of 29% in 2025 on 30.4 MW of net summer capacity, the 6th percentile of the 49 U.S. geothermal plants with at least 20 MW. The typical geothermal plant reached 66%. That equals about 106 days at full output out of 365.
0%Shaded: the middle half of geothermal plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Ormesa III | 29% |
| Geothermal plants, 75th percentile | 81% |
| Geothermal plants, median | 66% |
| Geothermal plants, 25th percentile | 51% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Ormesa III plant generating more or less than last year?
Generation at Ormesa III rose 74.1% from 2024 to 2025, from 44,416 MWh to 77,316 MWh.
| Period | MWh |
|---|---|
| 2024 | 44,416 |
| 2025 | 77,316 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 7,399 |
| November 2025 | 6,768 |
| October 2025 | 7,385 |
| September 2025 | 3,085 |
| August 2025 | 5,150 |
| July 2025 | 6,839 |
| June 2025 | 6,992 |
| May 2025 | 7,522 |
| April 2025 | 7,673 |
| March 2025 | 6,392 |
| February 2025 | 4,665 |
| January 2025 | 7,446 |
| December 2024 | 4,654 |
| November 2024 | 4,190 |
| October 2024 | 3,857 |
| September 2024 | 3,538 |
| August 2024 | 3,221 |
| July 2024 | 2,918 |
| June 2024 | 3,702 |
| May 2024 | 4,084 |
| April 2024 | 4,074 |
| March 2024 | 3,851 |
| February 2024 | 2,981 |
| January 2024 | 3,346 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Ormesa III plant, and when do they retire?
3 operable generators total 45.6 MW, with an average age of 22 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 1 | 22 | 47% | none reported |
| 2000s | 1 | 8 | 18% | none reported |
| 2020s | 1 | 16 | 35% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Out of service | Geothermal | 22 | 1989 | n/a |
| GBU | Operating | Geothermal | 8 | 2007 | n/a |
| OE301 | Operating | Geothermal | 16 | 2020 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Ormesa III plant?
EIA lists no joint owners for Ormesa III. Ormat Nevada Inc operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Ormesa III plant?
Ormesa III is in Holtville, Imperial County, California, at 32.7757° N, 115.2637° W. It sits in the Imperial Irrigation District balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which geothermal plants in California are similar in size?
California has 32 operable geothermal plants with 2,936 MW of capacity, and Ormesa III's 45.6 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| John L. Featherstone Plant | Imperial | 55 | 433,097 |
| Salton Sea Power Gen Co - Unit 3 | Imperial | 54 | 288,758 |
| Salton Sea Power Gen Co - Unit 4 | Imperial | 48 | 321,238 |
| Ormesa III | Imperial | 46 | 77,316 |
| CE Leathers | Imperial | 46 | 270,503 |
| Del Ranch Company | Imperial | 46 | 297,779 |
| Elmore Company | Imperial | 46 | 368,067 |
Source: EIA Forms EIA-860 and EIA-923, 2025.