Solar power plant, California

Paulsell solar power plant, California

Paulsell is a 35 MW power plant, 20 MW of it solar, in Stanislaus County, California, operated by Crow Creek Solar, LLC, and it generated 46,122 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 82nd percentile of U.S. solar plants. By 2025 generation it ranks 4,197th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

35 MWNameplate capacity
28%Capacity factor, 2025, solar units, 82nd percentile, on 20 MW net summer
4,197thU.S. rank by generation, 2025
1 yearAverage generator age, by MW

How hard does the Paulsell plant run compared with other solar plants?

The Paulsell plant's solar units had a capacity factor of 28% in 2025 on 20 MW of net summer capacity, the 82nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 102 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Paulsell28%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its solar generators only. Values above 105% are left out of the comparison.

Is the Paulsell plant generating more or less than last year?

Paulsell generated 46,122 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 3.6% ahead of the same months of 2025. 2024 has output for only 6 months, so the two years are not compared.

Net generation by period
PeriodMWh
202423,408
202546,122
2026 through August36,130
2025, same months34,872
Monthly generation, Jul 2024 to Aug 2026
MonthMWh
August 20265,689
July 20266,269
June 20266,015
May 20265,051
April 20263,887
March 20264,150
February 20262,743
January 20262,326
December 2025815
November 20252,056
October 20253,980
September 20254,399
August 20255,905
July 20256,410
June 20255,728
May 20255,324
April 20253,881
March 20252,973
February 20252,442
January 20252,209
December 20241,324
November 20242,020
October 20242,424
September 20242,879
August 20247,936
July 20246,825

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Paulsell plant?

Paulsell made 0.0% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 530th largest of 1,877 plants in California, the 4,234th largest of 14,327 in the U.S. and the 1,277th largest of 7,223 solar plants on its solar units alone. By 2025 generation it is the 484th largest of 1,608 generating plants in the state.

Paulsell within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)35107,4330.0%
Generation (MWh)46,122204,542,8980.0%
Solar capacity (MW)2024,6630.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Paulsell plant, and when do they retire?

2 operable generators total 35 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s235100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
PSLBAOperatingBatteries152024n/a
PSLPVOperatingSolar Photovoltaic202024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Paulsell plant?

EIA lists no joint owners for Paulsell. Crow Creek Solar, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What fuels does the Paulsell plant use?

Paulsell has capacity on 2 fuels: 57% solar and 43% battery and pumped storage. In 2025, solar made 106% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Solar2057.1%48,785
Battery and pumped storage1542.9%-2,663

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Paulsell plant?

Paulsell is in Crows Landing, Stanislaus County, California, at 37.3741° N, 121.1352° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and Paulsell's 20 MW is 0% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
RE Gaskell West 5 LLCKern2047,998
Little Bear 3Fresno2020,047
Wister SolarImperial2033,044
PaulsellStanislaus2048,785
AlmondKings2049,170
RB Inyokern Solar WDAT 1203 (CSG)Kern2058,295
White River Solar 2Tulare2049,169