Pioneer Generation Station, North Dakota

Pioneer Generation Station is a 897 MW natural gas power plant in Williams County, North Dakota, operated by Basin Electric Power Coop, and it generated 1,731,240 MWh in 2025 (Forms EIA-860 and EIA-923). That is 4.0% of the generation reported in North Dakota, and its capacity factor sits at the 55th percentile of U.S. natural gas plants. By 2025 generation it ranks 551st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

897 MWNameplate capacity
26%Capacity factor, 2025, 55th percentile, on 763 MW net summer
4.0%Of ND generation, 2025
3 yearsAverage generator age, by MW

How hard does Pioneer Generation Station run compared with other natural gas plants?

Pioneer Generation Station had a capacity factor of 26% in 2025 on 763 MW of net summer capacity, the 55th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 95 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Pioneer Generation Station26%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is Pioneer Generation Station generating more or less than last year?

Generation at Pioneer Generation Station rose 58.5% from 2024 to 2025, from 1,092,231 MWh to 1,731,240 MWh.

Net generation by period
PeriodMWh
20241,092,231
20251,731,240
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 2025116,713
November 2025111,599
October 2025117,186
September 2025167,685
August 2025226,085
July 2025234,606
June 2025184,766
May 2025143,661
April 202597,803
March 202586,114
February 2025108,626
January 2025136,395
December 202487,899
November 202478,023
October 202461,219
September 202492,690
August 2024140,807
July 2024147,305
June 202495,592
May 202483,551
April 202452,236
March 202468,856
February 202482,179
January 2024101,872

Source: EIA Form EIA-923, through August 2026.

How much of North Dakota's electricity comes from Pioneer Generation Station?

Pioneer Generation Station made 4.0% of the 42,873,330 MWh reported by North Dakota plants in 2025, from 8.2% of the state's 10,973 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 3rd largest of 62 plants in North Dakota, the 356th largest of 14,327 in the U.S. and the 187th largest of 1,962 natural gas plants. By 2025 generation it is the 7th largest of 57 generating plants in the state.

Pioneer Generation Station within North Dakota, 2025
MeasureThis plantNorth DakotaShare
Capacity (MW)89710,9738.2%
Generation (MWh)1,731,24042,873,3304.0%
Natural gas capacity (MW)8971,54658.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at Pioneer Generation Station, and when do they retire?

23 operable generators total 897 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1529333%none reported
2020s860467%none reported
Every generator, 23 in all
UnitStatusTechnologyMWIn servicePlanned retirement
01OperatingNatural Gas Fired Combustion Turbine612013n/a
02OperatingNatural Gas Fired Combustion Turbine612014n/a
03OperatingNatural Gas Fired Combustion Turbine612014n/a
11OperatingNatural Gas Internal Combustion Engine92017n/a
12OperatingNatural Gas Internal Combustion Engine92017n/a
13OperatingNatural Gas Internal Combustion Engine92017n/a
14OperatingNatural Gas Internal Combustion Engine92017n/a
15OperatingNatural Gas Internal Combustion Engine92017n/a
16OperatingNatural Gas Internal Combustion Engine92017n/a
17OperatingNatural Gas Internal Combustion Engine92017n/a
18OperatingNatural Gas Internal Combustion Engine92017n/a
19OperatingNatural Gas Internal Combustion Engine92017n/a
20OperatingNatural Gas Internal Combustion Engine92017n/a
21OperatingNatural Gas Internal Combustion Engine92017n/a
22OperatingNatural Gas Internal Combustion Engine92017n/a
04OperatingNatural Gas Fired Combustion Turbine2462025n/a
05OperatingNatural Gas Fired Combustion Turbine2462025n/a
31OperatingNatural Gas Internal Combustion Engine192025n/a
32OperatingNatural Gas Internal Combustion Engine192025n/a
33OperatingNatural Gas Internal Combustion Engine192025n/a
34OperatingNatural Gas Internal Combustion Engine192025n/a
35OperatingNatural Gas Internal Combustion Engine192025n/a
36OperatingNatural Gas Internal Combustion Engine192025n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns Pioneer Generation Station?

EIA lists no joint owners for Pioneer Generation Station. Basin Electric Power Coop operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is Pioneer Generation Station?

Pioneer Generation Station is in Williston, Williams County, North Dakota, at 48.2325° N, 103.9528° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.