Skip to main content
RateWatt

Natural gas power plant, Texas

Plant X natural gas power plant, Texas

Plant X is a 190 MW natural gas power plant in Lamb County, Texas, operated by Southwestern Public Service Co, and it generated 585,833 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 61st percentile of U.S. natural gas plants. By 2025 generation it ranks 1,151st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

190 MWNameplate capacity
35%Capacity factor, 2025, 61st percentile, on 190 MW net summer
0.1%Of TX generation, 2025
61 yearsAverage generator age, by MW

How hard does the Plant X plant run compared with other natural gas plants?

The Plant X plant had a capacity factor of 35% in 2025 on 190 MW of net summer capacity, the 61st percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 128 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Plant X35%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Plant X plant generating more or less than last year?

Generation at Plant X fell 28.2% from 2024 to 2025, from 815,693 MWh to 585,833 MWh.

3 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.

Net generation by period
PeriodMWh
2024815,693
2025585,833
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202565,312
November 202592,199
October 202549,952
September 202593,356
August 202593,293
July 202595,763
June 2025999
May 2025-281
April 2025-252
March 2025-276
February 202543,473
January 202552,295
December 202450,251
November 202470,851
October 202440,134
September 202483,272
August 2024111,674
July 2024119,691
June 202479,718
May 202470,970
April 202487,232
March 202454,087
February 202417,403
January 202430,410

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Plant X plant?

Plant X made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. By capacity it is the 345th largest of 1,023 plants in Texas, the 1,695th largest of 14,327 in the U.S. and the 725th largest of 1,962 natural gas plants. By 2025 generation it is the 223rd largest of 816 generating plants in the state.

Plant X within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)190195,9660.1%
Generation (MWh)585,833592,896,1760.1%
Natural gas capacity (MW)19081,5740.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Plant X plant, and when do they retire?

1 operable generator totals 190 MW, with an average age of 61 years weighted by capacity at the end of 2025. 190 MW, 100% of operable capacity, has a planned retirement, the first in 2027. 3 have already retired, totalling 244 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1960s1190100%2027
Capacity retiring by year
YearUnitsMW retiringShare of plant
20271190100%
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
4OperatingNatural Gas Steam Turbine19019642027
1RetiredNatural Gas Steam Turbine4819522023
2RetiredNatural Gas Steam Turbine9819532023
3RetiredNatural Gas Steam Turbine9819552022

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Plant X plant?

EIA lists no joint owners for Plant X. Southwestern Public Service Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Southwestern Public Service Co charge homes?

Southwestern Public Service Co, the operator of Plant X, had an average residential price of 13.94¢ per kWh and an average bill of $131 a month in 2025, 9% below the Texas average of 15.40¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Texas
Southwestern Public Service Co13.94¢$1319% lower
Texas average15.40¢$171
U.S. average17.23¢$15112% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Plant X plant?

Plant X is in Earth, Lamb County, Texas, at 34.1661° N, 102.4114° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Texas are similar in size?

Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Plant X's 190 MW is 0% of that.

Natural gas plants in Texas around this size
PlantCountyMW2025 MWh
ExxonMobil Baytown RefineryHarris2021,180,178
PearsallFrio202453,886
Power Station 4Galveston191516,802
Plant XLamb190585,537
Sam RayburnVictoria190162,099
Shell Deer ParkHarris182933,327
Timmerman Power PlantCaldwell180207,892

Source: EIA Forms EIA-860 and EIA-923, 2025.