Solar power plant, Michigan
Pullman Solar, LLC power plant, Michigan
Pullman Solar, LLC is a 20 MW solar power plant in Allegan County, Michigan, operated by AES Distributed Energy, and it generated 32,792 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 19th percentile of U.S. solar plants. By 2025 generation it ranks 4,627th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Pullman Solar, LLC plant run compared with other solar plants?
The Pullman Solar, LLC plant had a capacity factor of 19% in 2025 on 20 MW of net summer capacity, the 19th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 68 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Pullman Solar, LLC | 19% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Pullman Solar, LLC plant generating more or less than last year?
Generation at Pullman Solar, LLC fell 13.6% from 2024 to 2025, from 37,950 MWh to 32,792 MWh.
| Period | MWh |
|---|---|
| 2024 | 37,950 |
| 2025 | 32,792 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 663 |
| November 2025 | 1,393 |
| October 2025 | 2,395 |
| September 2025 | 3,020 |
| August 2025 | 3,235 |
| July 2025 | 3,890 |
| June 2025 | 4,818 |
| May 2025 | 4,462 |
| April 2025 | 3,422 |
| March 2025 | 3,167 |
| February 2025 | 1,428 |
| January 2025 | 899 |
| December 2024 | 569 |
| November 2024 | 899 |
| October 2024 | 3,297 |
| September 2024 | 4,014 |
| August 2024 | 4,674 |
| July 2024 | 5,152 |
| June 2024 | 4,802 |
| May 2024 | 4,798 |
| April 2024 | 4,112 |
| March 2024 | 2,828 |
| February 2024 | 2,313 |
| January 2024 | 492 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Pullman Solar, LLC plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| PULMN | Operating | Solar Photovoltaic | 20 | 2022 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Pullman Solar, LLC plant?
EIA lists no joint owners for Pullman Solar, LLC. AES Distributed Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Pullman Solar, LLC plant?
Pullman Solar, LLC is in Lee Township, Allegan County, Michigan, at 42.4716° N, 86.0969° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Michigan are similar in size?
Michigan has 70 operable solar plants with 1,967 MW of capacity, and Pullman Solar, LLC's 20 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Bingham Solar, LLC | Clinton | 20 | 41,783 |
| Temperance Solar, LLC | Monroe | 20 | 42,188 |
| Cement City Solar, LLC | Lenawee | 20 | 31,979 |
| Pullman Solar, LLC | Allegan | 20 | 32,792 |
| Macbeth Solar | Muskegon | 20 | 37,627 |
| Lyons Road | Shiawassee | 20 | 41,258 |
| Blue Elk IV Solar, LLC | Lenawee | 20 | 37,437 |
Source: EIA Forms EIA-860 and EIA-923, 2025.