Natural gas power plant, Florida

Seminole natural gas power plant, Florida

Seminole (FL) is a 1,898 MW power plant, 1,183 MW of it natural gas, in Putnam County, Florida, operated by Seminole Electric Cooperative Inc, and it generated 10,206,174 MWh in 2025 (Forms EIA-860 and EIA-923). That is 3.8% of the generation reported in Florida, and its capacity factor sits at the 90th percentile of U.S. natural gas plants. By 2025 generation it ranks 59th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

1,898 MWNameplate capacity
75%Capacity factor, 2025, natural gas units, 90th percentile, on 1,101 MW net summer
3.8%Of FL generation, 2025
17 yearsAverage generator age, by MW

How hard does the Seminole (FL) plant run compared with other natural gas plants?

The Seminole (FL) plant's natural gas units had a capacity factor of 75% in 2025 on 1,101 MW of net summer capacity, the 90th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 275 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Seminole (FL)75%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its natural gas generators only. Values above 105% are left out of the comparison.

Is the Seminole (FL) plant generating more or less than last year?

Generation at Seminole (FL) fell 2.7% from 2024 to 2025, from 10,494,608 MWh to 10,206,174 MWh. Through August 2026 it is running 5.5% behind the same months of 2025.

Net generation by period
PeriodMWh
202410,494,608
202510,206,174
2026 through August6,475,597
2025, same months6,852,366
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20261,090,251
July 20261,105,661
June 2026719,631
May 2026892,269
April 2026457,158
March 2026517,498
February 2026761,467
January 2026931,662
December 2025757,720
November 2025624,594
October 2025982,416
September 2025989,078
August 20251,067,824
July 20251,070,848
June 2025988,948
May 2025979,981
April 2025406,238
March 2025646,877
February 2025686,769
January 20251,004,881
December 2024799,943
November 2024432,626
October 2024880,230
September 2024979,568
August 20241,075,084
July 20241,075,865
June 20241,049,674
May 20241,050,329
April 2024873,647
March 2024745,506
February 2024499,944
January 20241,032,192

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Seminole (FL) plant?

Seminole (FL) made 3.8% of the 267,867,735 MWh reported by Florida plants in 2025, from 2.4% of the state's 79,936 MW of capacity. Its share of output is 1.6 times its share of capacity. By capacity it is the 12th largest of 331 plants in Florida, the 78th largest of 14,327 in the U.S. and the 94th largest of 1,962 natural gas plants on its natural gas units alone. By 2025 generation it is the 7th largest of 313 generating plants in the state.

Seminole (FL) within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)1,89879,9362.4%
Generation (MWh)10,206,174267,867,7353.8%
Natural gas capacity (MW)1,18352,8942.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Seminole (FL) plant, and when do they retire?

4 operable generators total 1,898 MW, with an average age of 17 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 1 has already retired, totalling 715 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1980s171538%none reported
2020s31,18362%none reported
Every generator, 6 in all
UnitStatusTechnologyMWIn servicePlanned retirement
2OperatingConventional Steam Coal7151984n/a
CT1OperatingNatural Gas Fired Combined Cycle3842023n/a
CT2OperatingNatural Gas Fired Combined Cycle3842023n/a
STOperatingNatural Gas Fired Combined Cycle4152023n/a
1RetiredConventional Steam Coal71519842024
3CancelledConventional Steam Coal850n/an/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Seminole (FL) plant?

EIA lists no joint owners for Seminole (FL). Seminole Electric Cooperative Inc operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What fuels does the Seminole (FL) plant use?

Seminole (FL) has capacity on 2 fuels: 62% natural gas and 38% coal. In 2025, natural gas made 71% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Natural gas1,18362.3%7,274,097
Coal71537.7%2,921,447

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Seminole (FL) plant?

Seminole (FL) is in Palatka, Putnam County, Florida, at 29.7331° N, 81.6328° W. It sits in the Seminole Electric Cooperative balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Florida are similar in size?

Florida has 68 operable natural gas plants with 52,894 MW of capacity, and Seminole (FL)'s 1,183 MW is 2% of that.

Natural gas plants in Florida around this size
PlantCountyMW2025 MWh
Cape CanaveralBrevard1,2956,958,351
RivieraPalm Beach1,2956,926,247
LauderdaleBroward1,216260,136
Seminole (FL)Putnam1,1837,274,097
AnclotePasco1,1122,015,598
Oleander Power Project LPBrevard994578,683
Midulla Generating StationHardee8533,537,285

Source: EIA Forms EIA-860 and EIA-923, 2025.