Hydro power plant, Alaska
Snettisham hydroelectric power plant, Alaska
Snettisham is a 78.2 MW hydro power plant in Juneau, Alaska, operated by Alaska Electric Light & Power Co., and it generated 285,260 MWh in 2025 (Forms EIA-860 and EIA-923). That is 3.8% of the generation reported in Alaska, and its capacity factor sits at the 70th percentile of U.S. hydro plants. By 2025 generation it ranks 2,040th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Snettisham plant run compared with other hydro plants?
The Snettisham plant had a capacity factor of 42% in 2025 on 78 MW of net summer capacity, the 70th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 152 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Snettisham | 42% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Snettisham plant generating more or less than last year?
Generation at Snettisham fell 14.3% from 2024 to 2025, from 332,682 MWh to 285,260 MWh.
| Period | MWh |
|---|---|
| 2024 | 332,682 |
| 2025 | 285,260 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 39,219 |
| November 2025 | 27,994 |
| October 2025 | 20,542 |
| September 2025 | 19,416 |
| August 2025 | 14,434 |
| July 2025 | 15,894 |
| June 2025 | 1,785 |
| May 2025 | 26,629 |
| April 2025 | 30,224 |
| March 2025 | 25,962 |
| February 2025 | 32,685 |
| January 2025 | 30,476 |
| December 2024 | 36,081 |
| November 2024 | 33,940 |
| October 2024 | 24,365 |
| September 2024 | 19,808 |
| August 2024 | 19,911 |
| July 2024 | 20,296 |
| June 2024 | 23,229 |
| May 2024 | 25,687 |
| April 2024 | 26,847 |
| March 2024 | 31,047 |
| February 2024 | 33,305 |
| January 2024 | 38,166 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Snettisham plant, and when do they retire?
3 operable generators total 78.2 MW, with an average age of 45 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 2 | 47 | 60% | none reported |
| 1990s | 1 | 31 | 40% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 24 | 1973 | n/a |
| 2 | Operating | Conventional Hydroelectric | 24 | 1973 | n/a |
| 3 | Operating | Conventional Hydroelectric | 31 | 1990 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Snettisham plant?
Alaska Industrial Dev&Exp Auth is the only joint owner reported for Snettisham, with 100.0%. Alaska Electric Light & Power Co. operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Alaska Electric Light & Power Co. charge homes?
Alaska Electric Light & Power Co., the operator of Snettisham, had an average residential price of 13.73¢ per kWh and an average bill of $125 a month in 2025, 47% below the Alaska average of 26.11¢.
| Measure | Price | Monthly bill | Against Alaska |
|---|---|---|---|
| Alaska Electric Light & Power Co. | 13.73¢ | $125 | 47% lower |
| Alaska average | 26.11¢ | $147 | |
| U.S. average | 17.23¢ | $151 | 34% lower |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Snettisham plant?
Snettisham is in Juneau, Juneau, Alaska, at 58.1415° N, 133.7370° W.
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Alaska are similar in size?
Alaska has 28 operable hydro plants with 475 MW of capacity, and Snettisham's 78.2 MW is 16% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Bradley Lake | Kenai Peninsula | 126 | 414,725 |
| Snettisham | Juneau | 78 | 285,260 |
| Eklutna Hydro Project | Matanuska Susitna | 44 | 157,577 |
Source: EIA Forms EIA-860 and EIA-923, 2025.