Solar power plant, North Carolina
Speedway Solar NC, LLC power plant, North Carolina
Speedway Solar NC, LLC is a 22.6 MW solar power plant in Cabarrus County, North Carolina, operated by Deriva Energy, and it generated 39,613 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 26th percentile of U.S. solar plants. By 2025 generation it ranks 4,376th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Speedway Solar NC, LLC plant run compared with other solar plants?
The Speedway Solar NC, LLC plant had a capacity factor of 20% in 2025 on 22.6 MW of net summer capacity, the 26th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 73 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Speedway Solar NC, LLC | 20% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Speedway Solar NC, LLC plant generating more or less than last year?
Generation at Speedway Solar NC, LLC rose 17.5% from 2024 to 2025, from 33,700 MWh to 39,613 MWh.
| Period | MWh |
|---|---|
| 2024 | 33,700 |
| 2025 | 39,613 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 2,207 |
| November 2025 | 2,846 |
| October 2025 | 3,075 |
| September 2025 | 4,508 |
| August 2025 | 3,269 |
| July 2025 | 5,304 |
| June 2025 | 4,912 |
| May 2025 | 3,019 |
| April 2025 | 2,926 |
| March 2025 | 3,434 |
| February 2025 | 1,905 |
| January 2025 | 2,208 |
| December 2024 | 2,113 |
| November 2024 | 1,823 |
| October 2024 | 2,076 |
| September 2024 | 2,700 |
| August 2024 | 4,082 |
| July 2024 | 3,289 |
| June 2024 | 3,627 |
| May 2024 | 3,695 |
| April 2024 | 3,627 |
| March 2024 | 2,743 |
| February 2024 | 1,998 |
| January 2024 | 1,927 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Speedway Solar NC, LLC plant, and when do they retire?
1 operable generator totals 22.6 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 23 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Solar Photovoltaic | 23 | 2021 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Speedway Solar NC, LLC plant?
Speedway Solar NC, LLC is the only joint owner reported for Speedway Solar NC, LLC, with 100.0%. Deriva Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Speedway Solar NC, LLC plant?
Speedway Solar NC, LLC is in Midland, Cabarrus County, North Carolina, at 35.2180° N, 80.5360° W. It sits in the Duke Energy Carolinas balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in North Carolina are similar in size?
North Carolina has 757 operable solar plants with 7,025 MW of capacity, and Speedway Solar NC, LLC's 22.6 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| East Nash PV2 | Nash | 23 | 52,978 |
| DD Fayetteville Solar NC LLC | Bladen | 23 | 39,433 |
| Stony Knoll Solar, LLC | Surry | 23 | 43,988 |
| Speedway Solar NC, LLC | Cabarrus | 23 | 39,613 |
| Ruff Solar LLC | Rutherford | 22 | 39,501 |
| Apple Data Center PV | Catawba | 21 | 29,279 |
| Holstein Plant | Scotland | 20 | 33,771 |
Source: EIA Forms EIA-860 and EIA-923, 2025.