Skip to main content
RateWatt

Hydro power plant, South Carolina

St Stephen hydroelectric power plant, South Carolina

St Stephen is a 84 MW hydro power plant in Berkeley County, South Carolina, operated by US Army Corps of Engineers, and it generated 161,076 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in South Carolina, and its capacity factor sits at the 25th percentile of U.S. hydro plants. By 2025 generation it ranks 2,800th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

84 MWNameplate capacity
22%Capacity factor, 2025, 25th percentile, on 84 MW net summer
0.2%Of SC generation, 2025
40 yearsAverage generator age, by MW

How hard does the St Stephen plant run compared with other hydro plants?

The St Stephen plant had a capacity factor of 22% in 2025 on 84 MW of net summer capacity, the 25th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 80 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
St Stephen22%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the St Stephen plant generating more or less than last year?

Generation at St Stephen fell 37.7% from 2024 to 2025, from 258,562 MWh to 161,076 MWh.

Net generation by period
PeriodMWh
2024258,562
2025161,076
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20251,835
November 2025584
October 20250
September 20250
August 202529,311
July 20251,660
June 202522,068
May 202530,176
April 202511,583
March 202520,503
February 202520,650
January 202522,706
December 202417,911
November 20246,703
October 202413,402
September 20245,796
August 202432,623
July 20241,201
June 20241,231
May 202429,885
April 202417,449
March 202446,778
February 202433,380
January 202452,203

Source: EIA Form EIA-923, through August 2026.

How much of South Carolina's electricity comes from the St Stephen plant?

St Stephen made 0.2% of the 103,930,530 MWh reported by South Carolina plants in 2025, from 0.3% of the state's 27,220 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 39th largest of 215 plants in South Carolina, the 2,917th largest of 14,327 in the U.S. and the 185th largest of 1,393 hydro plants. By 2025 generation it is the 28th largest of 197 generating plants in the state.

St Stephen within South Carolina, 2025
MeasureThis plantSouth CarolinaShare
Capacity (MW)8427,2200.3%
Generation (MWh)161,076103,930,5300.2%
Hydro capacity (MW)841,3486.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the St Stephen plant, and when do they retire?

3 operable generators total 84 MW, with an average age of 40 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1980s384100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric281985n/a
2OperatingConventional Hydroelectric281985n/a
3OperatingConventional Hydroelectric281985n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the St Stephen plant?

EIA lists no joint owners for St Stephen. US Army Corps of Engineers operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the St Stephen plant?

St Stephen is in St. Stephen, Berkeley County, South Carolina, at 33.4261° N, 79.9300° W. It sits in the South Carolina Public Service Authority balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in South Carolina are similar in size?

South Carolina has 29 operable hydro plants with 1,348 MW of capacity, and St Stephen's 84 MW is 6% of that.

Hydro plants in South Carolina around this size
PlantCountyMW2025 MWh
KeoweePickens15844,250
JefferiesBerkeley145233,504
Wateree HydroKershaw91137,253
St StephenBerkeley84161,076
WylieYork6098,649
Cedar Creek (SC)Lancaster45101,557
DearbornChester4570,180

Source: EIA Forms EIA-860 and EIA-923, 2025.