Solar power plant, Mississippi
Sumrall II Solar Farm, Mississippi
Sumrall II Solar Farm is a 52 MW solar power plant in Lamar County, Mississippi, operated by Onward Energy, and it generated 110,388 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Mississippi, and its capacity factor sits at the 59th percentile of U.S. solar plants. By 2025 generation it ranks 3,289th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Sumrall II Solar Farm plant run compared with other solar plants?
The Sumrall II Solar Farm plant had a capacity factor of 24% in 2025 on 52 MW of net summer capacity, the 59th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 88 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Sumrall II Solar Farm | 24% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Sumrall II Solar Farm plant generating more or less than last year?
Generation at Sumrall II Solar Farm rose 11.4% from 2024 to 2025, from 99,060 MWh to 110,388 MWh. Through August 2026 it is running 1.7% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 99,060 |
| 2025 | 110,388 |
| 2026 through August | 77,182 |
| 2025, same months | 78,546 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 11,978 |
| July 2026 | 12,075 |
| June 2026 | 10,367 |
| May 2026 | 9,424 |
| April 2026 | 9,878 |
| March 2026 | 10,007 |
| February 2026 | 7,348 |
| January 2026 | 6,105 |
| December 2025 | 5,007 |
| November 2025 | 7,195 |
| October 2025 | 9,116 |
| September 2025 | 10,524 |
| August 2025 | 10,701 |
| July 2025 | 11,895 |
| June 2025 | 11,499 |
| May 2025 | 10,998 |
| April 2025 | 10,704 |
| March 2025 | 10,145 |
| February 2025 | 6,491 |
| January 2025 | 6,113 |
| December 2024 | 5,747 |
| November 2024 | 5,632 |
| October 2024 | 9,297 |
| September 2024 | 7,947 |
| August 2024 | 11,277 |
| July 2024 | 9,164 |
| June 2024 | 9,686 |
| May 2024 | 9,995 |
| April 2024 | 9,849 |
| March 2024 | 7,340 |
| February 2024 | 7,211 |
| January 2024 | 5,915 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Sumrall II Solar Farm plant, and when do they retire?
1 operable generator totals 52 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 52 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| SUM2 | Operating | Solar Photovoltaic | 52 | 2017 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Sumrall II Solar Farm plant?
Renewables Pipeline Parent, LLC is the only joint owner reported for Sumrall II Solar Farm, with 100.0%. Onward Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Sumrall II Solar Farm plant?
Sumrall II Solar Farm is in Sumrall, Lamar County, Mississippi, at 31.3971° N, 89.4859° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Mississippi are similar in size?
Mississippi has 25 operable solar plants with 1,524 MW of capacity, and Sumrall II Solar Farm's 52 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Cane Creek | Clarke | 79 | 171,023 |
| Moonshot | Hancock | 79 | 174,404 |
| Meridian III | Lauderdale | 53 | 118,288 |
| Sumrall II Solar Farm | Lamar | 52 | 110,388 |
| Sumrall I Solar Farm | Lamar | 52 | 90,189 |
| Hattiesburg Solar Farm | Forrest | 50 | 87,794 |
Source: EIA Forms EIA-860 and EIA-923, 2025.