Thunderhead Wind Energy LLC is a 300 MW wind power plant in Antelope County, Nebraska, operated by Invenergy Services LLC, and it generated 1,102,888 MWh in 2025 (Forms EIA-860 and EIA-923). That is 2.8% of the generation reported in Nebraska, and its capacity factor sits at the 82nd percentile of U.S. wind plants. By 2025 generation it ranks 694th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

300 MWNameplate capacity
42%Capacity factor, 2025, 82nd percentile, on 300 MW net summer
2.8%Of NE generation, 2025
3 yearsAverage generator age, by MW

How hard does the Thunderhead Wind Energy LLC plant run compared with other wind plants?

The Thunderhead Wind Energy LLC plant had a capacity factor of 42% in 2025 on 300 MW of net summer capacity, the 82nd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 153 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Thunderhead Wind Energy LLC42%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Thunderhead Wind Energy LLC plant generating more or less than last year?

Generation at Thunderhead Wind Energy LLC fell 6.4% from 2024 to 2025, from 1,178,866 MWh to 1,102,888 MWh. Through August 2026 it is running 5.5% behind the same months of 2025.

Net generation by period
PeriodMWh
20241,178,866
20251,102,888
2026 through August672,361
2025, same months711,707
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202649,467
July 202658,058
June 202666,922
May 202686,930
April 202699,823
March 2026112,059
February 202695,025
January 2026104,077
December 2025114,533
November 202591,348
October 2025109,476
September 202575,824
August 202565,639
July 202571,571
June 202577,894
May 202562,068
April 202584,277
March 2025135,009
February 202595,956
January 2025119,293
December 202498,407
November 202496,538
October 2024114,976
September 2024107,115
August 202470,258
July 202462,128
June 202487,566
May 2024106,396
April 2024123,418
March 2024123,230
February 202498,409
January 202490,425

Source: EIA Form EIA-923, through August 2026.

How much of Nebraska's electricity comes from the Thunderhead Wind Energy LLC plant?

Thunderhead Wind Energy LLC made 2.8% of the 39,753,571 MWh reported by Nebraska plants in 2025, from 2.5% of the state's 12,150 MW of capacity. By capacity it is the 11th largest of 139 plants in Nebraska, the 1,045th largest of 14,327 in the U.S. and the 82nd largest of 1,358 wind plants. By 2025 generation it is the 7th largest of 121 generating plants in the state.

Thunderhead Wind Energy LLC within Nebraska, 2025
MeasureThis plantNebraskaShare
Capacity (MW)30012,1502.5%
Generation (MWh)1,102,88839,753,5712.8%
Wind capacity (MW)3003,5278.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Thunderhead Wind Energy LLC plant, and when do they retire?

1 operable generator totals 300 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1300100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingOnshore Wind Turbine3002022n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Thunderhead Wind Energy LLC plant?

EIA lists no joint owners for Thunderhead Wind Energy LLC. Invenergy Services LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Thunderhead Wind Energy LLC plant?

Thunderhead Wind Energy LLC is in Boone, Antelope County, Nebraska, at 42.0620° N, 98.2390° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Nebraska are similar in size?

Nebraska has 33 operable wind plants with 3,527 MW of capacity, and Thunderhead Wind Energy LLC's 300 MW is 9% of that.

Wind plants in Nebraska around this size
PlantCountyMW2025 MWh
Grande Prairie Wind FarmHolt4001,420,392
Rattlesnake Creek Wind ProjectDixon318896,555
Thunderhead Wind Energy LLCAntelope3001,102,888
Milligan 1 Wind FarmSaline300981,365
Haystack Wind Project, LLCWayne298801,761
Little Blue Wind Project, LLCWebster251913,015

Source: EIA Forms EIA-860 and EIA-923, 2025.