Nuclear power plant, Florida
Turkey Point nuclear power plant, Florida
Turkey Point is a 2,978 MW power plant, 1,754 MW of it nuclear, in Miami Dade County, Florida, operated by Florida Power & Light Co, and it generated 20,555,599 MWh in 2025 (Forms EIA-860 and EIA-923). That is 7.7% of the generation reported in Florida, and its capacity factor sits at the 63rd percentile of U.S. nuclear plants. By 2025 generation it ranks 7th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Turkey Point plant run compared with other nuclear plants?
The Turkey Point plant's nuclear units had a capacity factor of 96% in 2025 on 1,681 MW of net summer capacity, the 63rd percentile of the 54 U.S. nuclear plants with at least 20 MW. The typical nuclear plant reached 95%. That equals about 350 days at full output out of 365.
0%Shaded: the middle half of nuclear plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Turkey Point | 96% |
| Nuclear plants, 75th percentile | 97% |
| Nuclear plants, median | 95% |
| Nuclear plants, 25th percentile | 90% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its nuclear generators only. Values above 105% are left out of the comparison.
Is the Turkey Point plant generating more or less than last year?
Generation at Turkey Point fell 3.8% from 2024 to 2025, from 21,358,851 MWh to 20,555,599 MWh. Through August 2026 it is running 5.6% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 21,358,851 |
| 2025 | 20,555,599 |
| 2026 through August | 12,487,463 |
| 2025, same months | 13,225,017 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 1,929,072 |
| July 2026 | 1,919,964 |
| June 2026 | 1,840,694 |
| May 2026 | 1,570,373 |
| April 2026 | 1,164,817 |
| March 2026 | 1,226,649 |
| February 2026 | 1,102,632 |
| January 2026 | 1,733,262 |
| December 2025 | 1,845,374 |
| November 2025 | 1,764,965 |
| October 2025 | 2,002,307 |
| September 2025 | 1,717,936 |
| August 2025 | 1,850,929 |
| July 2025 | 1,973,080 |
| June 2025 | 1,803,674 |
| May 2025 | 1,609,836 |
| April 2025 | 1,325,035 |
| March 2025 | 1,284,255 |
| February 2025 | 1,622,964 |
| January 2025 | 1,755,244 |
| December 2024 | 1,752,971 |
| November 2024 | 1,426,799 |
| October 2024 | 1,553,320 |
| September 2024 | 1,914,881 |
| August 2024 | 2,006,208 |
| July 2024 | 2,004,563 |
| June 2024 | 1,917,408 |
| May 2024 | 1,991,662 |
| April 2024 | 1,746,780 |
| March 2024 | 1,740,241 |
| February 2024 | 1,453,003 |
| January 2024 | 1,851,015 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Turkey Point plant, and when do they retire?
7 operable generators total 2,978 MW, with an average age of 38 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 7 have already retired, totalling 818 MW.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 2 | 1,754 | 59% | none reported |
| 2000s | 5 | 1,224 | 41% | none reported |
Every generator, 14 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 3 | Operating | Nuclear | 877 | 1972 | n/a |
| 4 | Operating | Nuclear | 877 | 1973 | n/a |
| 5CA | Operating | Natural Gas Fired Combined Cycle | 472 | 2007 | n/a |
| 5CTA | Operating | Natural Gas Fired Combined Cycle | 188 | 2007 | n/a |
| 5CTB | Operating | Natural Gas Fired Combined Cycle | 188 | 2007 | n/a |
| 5CTC | Operating | Natural Gas Fired Combined Cycle | 188 | 2007 | n/a |
| 5CTD | Operating | Natural Gas Fired Combined Cycle | 188 | 2007 | n/a |
| ST1 | Retired | Natural Gas Steam Turbine | 402 | 1967 | 2016 |
| IC1 | Retired | Petroleum Liquids | 3 | 1968 | 2009 |
| IC2 | Retired | Petroleum Liquids | 3 | 1968 | 2009 |
| IC3 | Retired | Petroleum Liquids | 3 | 1968 | 2009 |
| IC4 | Retired | Petroleum Liquids | 3 | 1968 | 2009 |
| IC5 | Retired | Petroleum Liquids | 3 | 1968 | 2009 |
| ST2 | Retired | Petroleum Liquids | 402 | 1968 | 2013 |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Turkey Point plant?
EIA lists no joint owners for Turkey Point. Florida Power & Light Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Florida Power & Light Co charge homes?
Florida Power & Light Co, the operator of Turkey Point, had an average residential price of 14.62¢ per kWh and an average bill of $162 a month in 2025, 4% below the Florida average of 15.21¢.
| Measure | Price | Monthly bill | Against Florida |
|---|---|---|---|
| Florida Power & Light Co | 14.62¢ | $162 | 4% lower |
| Florida average | 15.21¢ | $168 | |
| U.S. average | 17.23¢ | $151 | 13% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
What fuels does the Turkey Point plant use?
Turkey Point has capacity on 2 fuels: 59% nuclear and 41% natural gas. In 2025, nuclear made 69% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Nuclear | 1,754 | 58.9% | 14,129,485 |
| Natural gas | 1,224 | 41.1% | 6,425,677 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Turkey Point plant?
Turkey Point is in Homestead, Miami Dade County, Florida, at 25.4356° N, 80.3308° W. It sits in the Florida Power & Light Company balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which nuclear plants in Florida are similar in size?
Florida has 2 operable nuclear plants with 3,914 MW of capacity, and Turkey Point's 1,754 MW is 45% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| St Lucie | St Lucie | 2,160 | 16,458,127 |
| Turkey Point | Miami Dade | 1,754 | 14,129,485 |
Source: EIA Forms EIA-860 and EIA-923, 2025.