Hydro power plant, Alaska
Tyee Lake Hydroelectric Facility, Alaska
Tyee Lake Hydroelectric Facility is a 22.6 MW hydro power plant in Wrangell Petersburg, Alaska, operated by Southeast Alaska Power Agency, and it generated 103,420 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.4% of the generation reported in Alaska, and its capacity factor sits at the 89th percentile of U.S. hydro plants. By 2025 generation it ranks 3,356th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Tyee Lake Hydroelectric Facility plant run compared with other hydro plants?
The Tyee Lake Hydroelectric Facility plant had a capacity factor of 52% in 2025 on 22.6 MW of net summer capacity, the 89th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 191 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Tyee Lake Hydroelectric Facility | 52% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Tyee Lake Hydroelectric Facility plant generating more or less than last year?
Generation at Tyee Lake Hydroelectric Facility fell 17.9% from 2024 to 2025, from 125,976 MWh to 103,420 MWh.
| Period | MWh |
|---|---|
| 2024 | 125,976 |
| 2025 | 103,420 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 12,432 |
| November 2025 | 8,340 |
| October 2025 | 6,217 |
| September 2025 | 5,795 |
| August 2025 | 7,717 |
| July 2025 | 6,206 |
| June 2025 | 4,418 |
| May 2025 | 6,183 |
| April 2025 | 10,886 |
| March 2025 | 12,089 |
| February 2025 | 12,637 |
| January 2025 | 10,500 |
| December 2024 | 9,605 |
| November 2024 | 9,490 |
| October 2024 | 9,332 |
| September 2024 | 10,826 |
| August 2024 | 12,058 |
| July 2024 | 11,304 |
| June 2024 | 5,964 |
| May 2024 | 10,614 |
| April 2024 | 11,109 |
| March 2024 | 13,168 |
| February 2024 | 11,291 |
| January 2024 | 11,215 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Tyee Lake Hydroelectric Facility plant, and when do they retire?
2 operable generators total 22.6 MW, with an average age of 42 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 2 | 23 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| UNIT1 | Operating | Conventional Hydroelectric | 11 | 1983 | n/a |
| UNIT2 | Operating | Conventional Hydroelectric | 11 | 1983 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Tyee Lake Hydroelectric Facility plant?
EIA lists no joint owners for Tyee Lake Hydroelectric Facility. Southeast Alaska Power Agency operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Tyee Lake Hydroelectric Facility plant?
Tyee Lake Hydroelectric Facility is in Wrangell, Wrangell Petersburg, Alaska, at 56.2164° N, 131.5043° W. It sits in the No BA balancing area.
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Alaska are similar in size?
Alaska has 28 operable hydro plants with 475 MW of capacity, and Tyee Lake Hydroelectric Facility's 22.6 MW is 5% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Eklutna Hydro Project | Matanuska Susitna | 44 | 157,577 |
| Terror Lake Microgrid | Kodiak Island | 34 | 147,315 |
| Swan Lake | Ketchikan Gateway | 23 | 77,633 |
| Tyee Lake Hydroelectric Facility | Wrangell Petersburg | 23 | 103,420 |
| Cooper Lake | Kenai Peninsula | 19 | 52,521 |
| Green Lake | Sitka | 19 | 38,490 |
| Blue Lake Hydro | Sitka | 16 | 80,882 |
Source: EIA Forms EIA-860 and EIA-923, 2025.