UCONN Cogen Facility, Connecticut

UCONN Cogen Facility is a 25.7 MW natural gas power plant in Tolland County, Connecticut, operated by University of Connecticut, and it generated 110,500 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Connecticut, and its capacity factor sits at the 71st percentile of U.S. natural gas plants. By 2025 generation it ranks 3,288th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

25.7 MWNameplate capacity
50%Capacity factor, 2025, 71st percentile, on 24.6 MW net summer
0.3%Of CT generation, 2025
19 yearsAverage generator age, by MW

How hard does the UCONN Cogen Facility plant run compared with other natural gas plants?

The UCONN Cogen Facility plant had a capacity factor of 50% in 2025 on 24.6 MW of net summer capacity, the 71st percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 184 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
UCONN Cogen Facility50%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the UCONN Cogen Facility plant generating more or less than last year?

Generation at UCONN Cogen Facility fell 10.0% from 2024 to 2025, from 122,717 MWh to 110,500 MWh. Through August 2026 it is running 1.2% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024122,717
2025110,500
2026 through August80,711
2025, same months79,759
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202611,920
July 202611,753
June 202610,242
May 20262,507
April 202611,104
March 202611,319
February 202610,797
January 202611,069
November 20257,595
October 202511,349
September 202511,797
August 202511,496
July 202512,134
June 202510,943
May 20251,419
April 202511,067
March 202511,013
February 202510,542
January 202511,145
December 202410,784
November 202410,008
October 202411,418
September 202411,074
August 202411,573
July 202412,000
June 202410,930
May 20243,230
April 20249,789
March 202410,683
February 202410,577
January 202410,651

Source: EIA Form EIA-923, through August 2026.

How much of Connecticut's electricity comes from the UCONN Cogen Facility plant?

UCONN Cogen Facility made 0.3% of the 43,744,586 MWh reported by Connecticut plants in 2025, from 0.2% of the state's 10,990 MW of capacity. By capacity it is the 31st largest of 182 plants in Connecticut, the 4,540th largest of 14,327 in the U.S. and the 1,242nd largest of 1,962 natural gas plants. By 2025 generation it is the 16th largest of 168 generating plants in the state.

UCONN Cogen Facility within Connecticut, 2025
MeasureThis plantConnecticutShare
Capacity (MW)2610,9900.2%
Generation (MWh)110,50043,744,5860.3%
Natural gas capacity (MW)264,9570.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the UCONN Cogen Facility plant, and when do they retire?

4 operable generators total 25.7 MW, with an average age of 19 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s426100%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CGT1OperatingNatural Gas Fired Combined Cycle72006n/a
CGT2OperatingNatural Gas Fired Combined Cycle72006n/a
CGT3OperatingNatural Gas Fired Combined Cycle72006n/a
STG1OperatingNatural Gas Fired Combined Cycle52006n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the UCONN Cogen Facility plant?

EIA lists no joint owners for UCONN Cogen Facility. University of Connecticut operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the UCONN Cogen Facility plant?

UCONN Cogen Facility is in Storrs, Tolland County, Connecticut, at 41.8092° N, 72.2542° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Connecticut are similar in size?

Connecticut has 47 operable natural gas plants with 4,957 MW of capacity, and UCONN Cogen Facility's 25.7 MW is 1% of that.

Natural gas plants in Connecticut around this size
PlantCountyMW2025 MWh
Pfizer Groton PlantNew London3867,539
Kimberly Clark-Unit 1,2,3Litchfield36233,323
Pratt & WhitneyHartford2665,917
UCONN Cogen FacilityTolland26108,814
Bridgeport Fuel Cell, LLCFairfield1790,449
Rand Whitney CHP PlantNew London17133,369
Foxwoods CoGenNew London1610,834

Source: EIA Forms EIA-860 and EIA-923, 2025.