Natural gas power plant, California
Walnut Creek Energy Park natural gas power plant, California
Walnut Creek Energy Park is a 500 MW natural gas power plant in Los Angeles County, California, operated by Walnut Creek LLC, and it generated 45,060 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 10th percentile of U.S. natural gas plants. By 2025 generation it ranks 4,221st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Walnut Creek Energy Park plant run compared with other natural gas plants?
The Walnut Creek Energy Park plant had a capacity factor of 1% in 2025 on 501 MW of net summer capacity, the 10th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 4 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Walnut Creek Energy Park | 1% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Walnut Creek Energy Park plant generating more or less than last year?
Generation at Walnut Creek Energy Park fell 83.8% from 2024 to 2025, from 278,182 MWh to 45,060 MWh. Through August 2026 it is running 79.8% ahead of the same months of 2025. Only 7 months of 2026 have been reported for this plant.
5 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.
| Period | MWh |
|---|---|
| 2024 | 278,182 |
| 2025 | 45,060 |
| 2026 through August | 53,110 |
| 2025, same months | 29,540 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 36,955 |
| July 2026 | 11,536 |
| June 2026 | 2,721 |
| May 2026 | 1,028 |
| March 2026 | 1,382 |
| February 2026 | -196 |
| January 2026 | -316 |
| December 2025 | 2,567 |
| November 2025 | -218 |
| October 2025 | -320 |
| September 2025 | 12,252 |
| August 2025 | 17,572 |
| July 2025 | -65 |
| June 2025 | 4,585 |
| May 2025 | 2,013 |
| April 2025 | 1,239 |
| March 2025 | 2,798 |
| February 2025 | 1,119 |
| January 2025 | 1,518 |
| December 2024 | 2,074 |
| November 2024 | 826 |
| October 2024 | 17,247 |
| September 2024 | 28,483 |
| August 2024 | 49,565 |
| July 2024 | 67,263 |
| June 2024 | 27,484 |
| May 2024 | 4,671 |
| April 2024 | 6,538 |
| March 2024 | 13,835 |
| February 2024 | 13,270 |
| January 2024 | 46,926 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Walnut Creek Energy Park plant, and when do they retire?
5 operable generators total 500 MW, with an average age of 12 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 5 | 500 | 100% | none reported |
Every generator, 5 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GT1 | Operating | Natural Gas Fired Combustion Turbine | 100 | 2013 | n/a |
| GT2 | Operating | Natural Gas Fired Combustion Turbine | 100 | 2013 | n/a |
| GT3 | Operating | Natural Gas Fired Combustion Turbine | 100 | 2013 | n/a |
| GT4 | Operating | Natural Gas Fired Combustion Turbine | 100 | 2013 | n/a |
| GT5 | Operating | Natural Gas Fired Combustion Turbine | 100 | 2013 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Walnut Creek Energy Park plant?
EIA lists no joint owners for Walnut Creek Energy Park. Walnut Creek LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Walnut Creek Energy Park plant?
Walnut Creek Energy Park is in Industry, Los Angeles County, California, at 34.0087° N, 117.9449° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in California are similar in size?
California has 304 operable natural gas plants with 40,211 MW of capacity, and Walnut Creek Energy Park's 500 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Cosumnes Power Plant | Sacramento | 557 | 3,500,786 |
| Harbor | Los Angeles | 548 | 89,429 |
| El Segundo Energy Center LLC | Los Angeles | 537 | 45,090 |
| Walnut Creek Energy Park | Los Angeles | 500 | 45,060 |
| Panoche Energy Center | Fresno | 432 | 760,356 |
| Watson Cogeneration | Los Angeles | 405 | 1,783,717 |
| Pio Pico Energy Center | San Diego | 395 | 46,864 |
Source: EIA Forms EIA-860 and EIA-923, 2025.