Skip to main content
RateWatt

Natural gas power plant, Georgia

Walton County Energy Facility, Georgia

Walton County Energy Facility is a 494 MW natural gas power plant in Walton County, Georgia, operated by Oglethorpe Power Corporation, and it generated 353,884 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Georgia, and its capacity factor sits at the 33rd percentile of U.S. natural gas plants. By 2025 generation it ranks 1,760th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

494 MWNameplate capacity
9%Capacity factor, 2025, 33rd percentile, on 450 MW net summer
0.2%Of GA generation, 2025
24 yearsAverage generator age, by MW

How hard does the Walton County Energy Facility plant run compared with other natural gas plants?

The Walton County Energy Facility plant had a capacity factor of 9% in 2025 on 450 MW of net summer capacity, the 33rd percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 33 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Walton County Energy Facility9%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Walton County Energy Facility plant generating more or less than last year?

Walton County Energy Facility generated 353,884 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 10 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024313,842
2025353,884
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20258,472
November 20255,387
October 202512,539
September 202563,576
August 202546,530
July 202590,494
June 202564,185
May 202538,605
April 202517,530
March 20250
February 20250
January 20256,568
December 20248,253
November 202421,815
October 202437,910
September 202449,936
August 202487,518
July 202484,057
June 20240
May 20249,064
April 20246,425
March 20240
February 2024517
January 20248,347

Source: EIA Form EIA-923, through August 2026.

How much of Georgia's electricity comes from the Walton County Energy Facility plant?

Walton County Energy Facility made 0.2% of the 144,967,352 MWh reported by Georgia plants in 2025, from 1.2% of the state's 42,719 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 26th largest of 263 plants in Georgia, the 746th largest of 14,327 in the U.S. and the 463rd largest of 1,962 natural gas plants. By 2025 generation it is the 32nd largest of 242 generating plants in the state.

Walton County Energy Facility within Georgia, 2025
MeasureThis plantGeorgiaShare
Capacity (MW)49442,7191.2%
Generation (MWh)353,884144,967,3520.2%
Natural gas capacity (MW)49418,4662.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Walton County Energy Facility plant, and when do they retire?

3 operable generators total 494 MW, with an average age of 24 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s3494100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
101GOperatingNatural Gas Fired Combustion Turbine1652001n/a
102GOperatingNatural Gas Fired Combustion Turbine1652001n/a
103GOperatingNatural Gas Fired Combustion Turbine1652001n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Walton County Energy Facility plant?

Walton County Power, LLC. is the only joint owner reported for Walton County Energy Facility, with 100.0%. Oglethorpe Power Corporation operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Walton County Energy Facility plant?

Walton County Energy Facility is in Monroe, Walton County, Georgia, at 33.8148° N, 83.6954° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Georgia are similar in size?

Georgia has 30 operable natural gas plants with 18,466 MW of capacity, and Walton County Energy Facility's 494 MW is 3% of that.

Natural gas plants in Georgia around this size
PlantCountyMW2025 MWh
Sewell Creek EnergyPolk570415,682
Chattahoochee Energy FacilityHeard5403,696,404
Hawk Road FacilityHeard495722,241
Walton County Energy FacilityWalton494353,884
Doyle Energy FacilityWalton40926,542
MPC GeneratingWalton386127,089
Hartwell Energy FacilityHart36093,880

Source: EIA Forms EIA-860 and EIA-923, 2025.