Wansley Combined Cycle natural gas power plant, Georgia

Wansley Combined Cycle is a 1,239 MW natural gas power plant in Heard County, Georgia, operated by Southern Power Co, and it generated 7,632,672 MWh in 2025 (Forms EIA-860 and EIA-923). That is 5.3% of the generation reported in Georgia, and its capacity factor sits at the 89th percentile of U.S. natural gas plants. By 2025 generation it ranks 112th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

1,239 MWNameplate capacity
74%Capacity factor, 2025, 89th percentile, on 1,185 MW net summer
5.3%Of GA generation, 2025
23 yearsAverage generator age, by MW

How hard does the Wansley Combined Cycle plant run compared with other natural gas plants?

The Wansley Combined Cycle plant had a capacity factor of 74% in 2025 on 1,185 MW of net summer capacity, the 89th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 268 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Wansley Combined Cycle74%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Wansley Combined Cycle plant generating more or less than last year?

Generation at Wansley Combined Cycle fell 2.5% from 2024 to 2025, from 7,831,043 MWh to 7,632,672 MWh. Through August 2026 it is running 3.3% behind the same months of 2025.

Net generation by period
PeriodMWh
20247,831,043
20257,632,672
2026 through August5,223,652
2025, same months5,400,303
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026742,105
July 2026769,599
June 2026713,635
May 2026501,157
April 2026748,245
March 2026667,027
February 2026498,868
January 2026583,016
December 2025577,330
November 2025617,513
October 2025718,778
September 2025318,748
August 2025700,939
July 2025781,324
June 2025700,851
May 2025728,075
April 2025769,613
March 2025528,766
February 2025467,861
January 2025722,874
December 2024598,608
November 2024533,778
October 2024631,350
September 2024747,124
August 2024776,639
July 2024789,412
June 2024650,906
May 2024489,006
April 2024655,066
March 2024643,478
February 2024592,414
January 2024723,262

Source: EIA Form EIA-923, through August 2026.

How much of Georgia's electricity comes from the Wansley Combined Cycle plant?

Wansley Combined Cycle made 5.3% of the 144,967,352 MWh reported by Georgia plants in 2025, from 2.9% of the state's 42,719 MW of capacity. Its share of output is 1.8 times its share of capacity. By capacity it is the 7th largest of 263 plants in Georgia, the 208th largest of 14,327 in the U.S. and the 79th largest of 1,962 natural gas plants. By 2025 generation it is the 8th largest of 242 generating plants in the state.

Wansley Combined Cycle within Georgia, 2025
MeasureThis plantGeorgiaShare
Capacity (MW)1,23942,7192.9%
Generation (MWh)7,632,672144,967,3525.3%
Natural gas capacity (MW)1,23918,4666.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Wansley Combined Cycle plant, and when do they retire?

6 operable generators total 1,239 MW, with an average age of 23 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s61,239100%none reported
Every generator, 6 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CT6AOperatingNatural Gas Fired Combined Cycle2032002n/a
CT6BOperatingNatural Gas Fired Combined Cycle2032002n/a
CT7AOperatingNatural Gas Fired Combined Cycle2032002n/a
CT7BOperatingNatural Gas Fired Combined Cycle2032002n/a
ST6OperatingNatural Gas Fired Combined Cycle2132002n/a
ST7OperatingNatural Gas Fired Combined Cycle2132002n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Wansley Combined Cycle plant?

EIA lists no joint owners for Wansley Combined Cycle. Southern Power Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Wansley Combined Cycle plant?

Wansley Combined Cycle is in Franklin, Heard County, Georgia, at 33.4064° N, 85.0370° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Georgia are similar in size?

Georgia has 30 operable natural gas plants with 18,466 MW of capacity, and Wansley Combined Cycle's 1,239 MW is 7% of that.

Natural gas plants in Georgia around this size
PlantCountyMW2025 MWh
McIntosh Combined Cycle FacilityEffingham1,3777,857,050
Wansley Combined CycleHeard1,2397,632,672
Thomas A Smith Energy FacilityMurray1,1928,251,810
Tenaska Georgia Generation FacilityHeard1,09997,349
DahlbergJackson919266,946