Hydro power plant, Georgia
West Point hydroelectric power plant, Georgia
West Point (GA) is a 73.3 MW hydro power plant in Troup County, Georgia, operated by USCE-Mobile District, and it generated 158,987 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Georgia, and its capacity factor sits at the 23rd percentile of U.S. hydro plants. By 2025 generation it ranks 2,813th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the West Point (GA) plant run compared with other hydro plants?
The West Point (GA) plant had a capacity factor of 21% in 2025 on 87 MW of net summer capacity, the 23rd percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 76 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| West Point (GA) | 21% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the West Point (GA) plant generating more or less than last year?
Generation at West Point (GA) fell 12.1% from 2024 to 2025, from 180,961 MWh to 158,987 MWh.
| Period | MWh |
|---|---|
| 2024 | 180,961 |
| 2025 | 158,987 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 7,119 |
| November 2025 | 6,700 |
| October 2025 | 7,387 |
| September 2025 | 11,972 |
| August 2025 | 16,560 |
| July 2025 | 15,395 |
| June 2025 | 16,366 |
| May 2025 | 20,869 |
| April 2025 | 16,230 |
| March 2025 | 12,724 |
| February 2025 | 18,674 |
| January 2025 | 8,991 |
| December 2024 | 9,554 |
| November 2024 | 8,769 |
| October 2024 | 8,365 |
| September 2024 | 17,377 |
| August 2024 | 12,957 |
| July 2024 | 13,150 |
| June 2024 | 7,711 |
| May 2024 | 10,546 |
| April 2024 | 17,745 |
| March 2024 | 31,982 |
| February 2024 | 20,071 |
| January 2024 | 22,734 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the West Point (GA) plant, and when do they retire?
3 operable generators total 73.3 MW, with an average age of 50 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 3 | 73 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 3 | 1975 | n/a |
| 2 | Operating | Conventional Hydroelectric | 35 | 1975 | n/a |
| 3 | Operating | Conventional Hydroelectric | 35 | 1975 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the West Point (GA) plant?
EIA lists no joint owners for West Point (GA). USCE-Mobile District operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the West Point (GA) plant?
West Point (GA) is in West Point, Troup County, Georgia, at 32.9187° N, 85.1887° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Georgia are similar in size?
Georgia has 27 operable hydro plants with 1,550 MW of capacity, and West Point (GA)'s 73.3 MW is 5% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Buford | Forsyth | 131 | 142,644 |
| Allatoona | Bartow | 87 | 110,538 |
| West Point (GA) | Troup | 73 | 158,987 |
| Tallulah Falls | Habersham | 72 | 106,179 |
| Oliver Dam | Muscogee | 60 | 120,256 |
| Sinclair Dam | Baldwin | 45 | 104,972 |
Source: EIA Forms EIA-860 and EIA-923, 2025.